 Buying Under Construction Apt, Lots of question

views
     
aaronpang
post Apr 6 2007, 12:35 PM

Cat Exterminator
******
Senior Member
1,979 posts

Joined: Jan 2003
From: Kuala Lumpur
QUOTE(ganz @ Apr 5 2007, 01:53 PM)
2. if the construction delay from expected completion date .. do i entitle any LAD?

*
Depends on your S&P - those modified S&P has got loop holes to allow the developer to escape paying you your LAD. It ususally applies to those services aprtments and condos that have commercial title.

QUOTE(ganz @ Apr 5 2007, 01:53 PM)
3. how long do I have to pay the interest to bank if the developer failed to complete the construction at all??

*
Continue to service your loan principal until forever... actually if the project abandoned you're screwed. If you got money start servicing the loan until you no longer owe the bank money...

QUOTE(ganz @ Apr 5 2007, 01:53 PM)
4. and the most important thing..what should I do (beside praying to GOD that the construction can be completed..) sad.gif

*
Not much it's not up to you... you can only collect LAD and pester the developer!



QUOTE(ganz @ Apr 6 2007, 10:50 AM)
Merge Holding (contractor Juta Permai) at Subang 2.. it Damai Apartment.. since i'm staying just at kota damansara.. i always go there to look the progress (from far view).. however, the development of the surrounding area seem in good shape (double storey house) only my apartment seems stall a bit..(3-4 month i think)..

but worried me is that. i bought this house in 2005 it already 2 years.. n i getting married this august..n i thought that i can go to my new house after i married..

sad.gif
*
When is it due for completion...?

Anyway there are reasons why projects tend to stop for months at a time sometimes its due to worker issues, delay in materials... or stop work order... you'll have to inquire with the developer.

BTW if the surrounding area is by the same developer it can happen when they reassign their work force to finish other projects first and will get back to your apartment at a later stage.

This post has been edited by aaronpang: Apr 6 2007, 12:39 PM
aaronpang
post Apr 7 2007, 02:09 AM

Cat Exterminator
******
Senior Member
1,979 posts

Joined: Jan 2003
From: Kuala Lumpur
QUOTE(mIssfROGY @ Apr 6 2007, 02:17 PM)
Like mine, project also been delayed like more than half year oredi (thank god nearly complete). but when i wanna start paying my principal, the bank would not allow me sad.gif Every month i only can service the interest alone....its killing me...
*
QUOTE(ganz @ Apr 6 2007, 03:23 PM)
I burn neraly quater of my monthly income to pay the interest..

*
Is this your first time buying property?

Banks really makan consumers when it comes to housing loan... to be honest I see no point in purchasing property thats not ready built and servicing the loan for nothing in return!

Just to share my personal buying experience. I waited for the housing project to complete and purchased a fully completed house from the developer at launch price developer didn't even markup the purchase price... because of competition in Puchong and the soft property market.

End of the day I saved a bundle on my loan and still got a completed house at the same price as those who purchased units much earlier before construction.

I fully support the government to adopt the build and sell concept! thumbup.gif not like now where they sell then build (or abandon) shakehead.gif

QUOTE(ganz @ Apr 6 2007, 03:23 PM)
by the way.. thanks for the prompt reply.. i'm going to the developer office next week..
*
Wish you all the best, and hopefully the developer will have a good answer for you! icon_rolleyes.gif

Cheers!

 