QUOTE(JenifferBlue9491 @ Dec 18 2019, 11:10 PM)
I have hold the stakeholder sum because the developer delay in handling my defects.
I want to claim for my maintenance fees for 3 months because of defect delay.
I have already sign off all my defects form
My question is... Will the developer able to claim back that stakeholder because I have sign off? Or will the solicitor need my acknowledgement that all defect is settle?
I WANT MY MAINTENANCE FEES TO BE WAIVED
If previously u issue a letter pursuant to Clause 29/30 (depending on old / new schedule H)I want to claim for my maintenance fees for 3 months because of defect delay.
I have already sign off all my defects form
My question is... Will the developer able to claim back that stakeholder because I have sign off? Or will the solicitor need my acknowledgement that all defect is settle?
I WANT MY MAINTENANCE FEES TO BE WAIVED
1) based on the act, developer's architect need to issue a certificate of completion defect rectification and forward to stakeholder lawyer before they can release the money to developer.
2) with the defect form sign off by you.
As for waive for your maintenance fees, i d't think that will work under the act. Everyone must pay for the maintenance charges and sinking fund for the property they bought, the only way is you demand the developer pay on your behalf.
Feb 26 2020, 10:16 AM