Hi,

1)would like to know how long does TNB take to supply electric to new house once registration done by Licensed Electrical Wiring Contractor?

2)Who actually should apply for the electrical connection?Developer or buyer?

TQ
Richard
post Oct 20 2016, 09:01 PM

Regular
******
Senior Member
1,083 posts

Joined: Jan 2003
From: Kota Kinabalu


QUOTE(thenuts15 @ Oct 3 2016, 02:06 AM)
Hi,

1)would like to know how long does TNB take to supply electric to new house once registration done by Licensed Electrical Wiring Contractor?

2)Who actually should apply for the electrical connection?Developer or buyer?

TQ
*
I refer to my own SESB (Sabah Electricity Sdn Bhd),

1) Within a week..

2) The electricity meter applicant will have to sign an agreement with SESB make a deposit for the meter and the meter installation is completed within a week, usually two working days..

You need to call up the electrical meter section of SESB to follow up..

I believe TNB should be the same process as the both companies (SESB and TNB) ESAH (Electricity Supply Application Handbook) is similar..

Refer here https://www.tnb.com.my/commercial-industria...cal-contractors
TSthenuts15
post Oct 21 2016, 03:45 PM

Casual
***
Junior Member
385 posts

Joined: Oct 2013
Noted,thank you very much

 