 Construction Progress for High Rise Property, Average speed to complete one floor

For high rise property (such as condo and service apartment, upon completion of piling and other ground works, what is the average speed to complete for one floor? Be it car park level or residential floor.
 
Less than 1 week, 1 <= t [ 5 ] ** [41.67%]
Within 1-2 weeks, 1 < t <= 2 [ 2 ] ** [16.67%]
Within 2-3 weeks, 2 < t <= 3 [ 3 ] ** [25.00%]
Within 3-4 weeks, 3 < t <= 4 [ 1 ] ** [8.33%]
More than 4 weeks, t > 4 [ 1 ] ** [8.33%]
Total Votes: 12
Guests cannot vote 
views
     
kochin
post Aug 3 2016, 11:51 AM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


have done 4 days cycle for approx 17k sf floor plate previously.
shear walls all around no less and no brickwalls.

but not every floor also achieve 4 days cycle lah.

kochin
post Aug 3 2016, 12:09 PM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


QUOTE(WahBiang @ Aug 3 2016, 12:07 PM)
Actually, how to differentiate all these type of walls and its pros n cons?
*
mr. google is your best friend.

 