Welcome Guest ( Log In | Register )

Outline · [ Standard ] · Linear+

 Construction Progress for High Rise Property, Average speed to complete one floor

For high rise property (such as condo and service apartment, upon completion of piling and other ground works, what is the average speed to complete for one floor? Be it car park level or residential floor.
 
Less than 1 week, 1 <= t [ 5 ] ** [41.67%]
Within 1-2 weeks, 1 < t <= 2 [ 2 ] ** [16.67%]
Within 2-3 weeks, 2 < t <= 3 [ 3 ] ** [25.00%]
Within 3-4 weeks, 3 < t <= 4 [ 1 ] ** [8.33%]
More than 4 weeks, t > 4 [ 1 ] ** [8.33%]
Total Votes: 12
Guests cannot vote 
views
     
enriquelee
post Jul 15 2016, 10:27 AM

Don't ask for more, ask for COKE
********
All Stars
10,510 posts

Joined: Jan 2003
From: Atlanta

It depends on many factors.
enriquelee
post Jul 15 2016, 01:06 PM

Don't ask for more, ask for COKE
********
All Stars
10,510 posts

Joined: Jan 2003
From: Atlanta

QUOTE(WahBiang @ Jul 15 2016, 12:35 PM)
Factors such as? Say they need complete by 48 months?
*
1) Type of formwork use
2) Floor area per floor
3) Complexity of the structure
4) Design

This is just for progress of structure works. For architectural works, it normally take around 7 to 8 months from concrete topping up works.
enriquelee
post Jul 21 2016, 10:46 AM

Don't ask for more, ask for COKE
********
All Stars
10,510 posts

Joined: Jan 2003
From: Atlanta

QUOTE(xproc @ Jul 18 2016, 09:04 PM)
aluminium formwork
*
Aluminium formwork usually take around 7 days circle per floor for typical floor.

QUOTE(kabyss87 @ Jul 20 2016, 11:53 PM)
But generally, as a person without knowledge on how construction works, what kind of physical sign we should look for to determine whether a construction was slow/fast in progress?

i'm only determine the progress looking at the rate they built up the floors.. please enlighten..  smile.gif
*
To judge whether a condominium project is on time or not maybe one can calculate is such a way,

From the SPA VP date, minus 4 month for getting CCC after CPC, then minus 8 months for general architectural works.

Then use this date minus current date, this will be your total month to carry out the structural works. Then use this period divide by total story of your condominium, that will let you judge how many days in average are needed per floor in order to deliver the project on time.

But some floor will take longer time to complete, such as the podium, 1st typical floor, transfer floor, non typical floor and etc.

Hope this help.
enriquelee
post Jul 25 2016, 10:36 AM

Don't ask for more, ask for COKE
********
All Stars
10,510 posts

Joined: Jan 2003
From: Atlanta

QUOTE(xproc @ Jul 23 2016, 06:33 PM)
i been told some projects can goes as fast as average 4 days per floor,

maybe they during concrete setting time they can do all the  rebar and formwork installation for upper floor...
*
Fastest i heard before is 6 days in average. 4 days maybe happened once in a blue moon.

QUOTE(WahBiang @ Jul 23 2016, 07:34 PM)
Thats fast till scary.. but if compared wih China, thats nothing..
*
From my previous study China those super highrise (above 70 storey), they can achieve 3 days circle in average. Center core is reinforced concrete while others are steel structure with bondeck.

 

Change to:
| Lo-Fi Version
0.0453sec    1.07    8 queries    GZIP Disabled
Time is now: 28th November 2025 - 07:07 PM