It depends on many factors.
Construction Progress for High Rise Property, Average speed to complete one floor
Construction Progress for High Rise Property, Average speed to complete one floor
|
|
Jul 15 2016, 10:27 AM
Return to original view | Post
#1
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,510 posts Joined: Jan 2003 From: Atlanta |
It depends on many factors.
|
|
|
|
|
|
Jul 15 2016, 01:06 PM
Return to original view | Post
#2
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,510 posts Joined: Jan 2003 From: Atlanta |
QUOTE(WahBiang @ Jul 15 2016, 12:35 PM) 1) Type of formwork use2) Floor area per floor 3) Complexity of the structure 4) Design This is just for progress of structure works. For architectural works, it normally take around 7 to 8 months from concrete topping up works. |
|
|
Jul 21 2016, 10:46 AM
Return to original view | Post
#3
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,510 posts Joined: Jan 2003 From: Atlanta |
QUOTE(xproc @ Jul 18 2016, 09:04 PM) Aluminium formwork usually take around 7 days circle per floor for typical floor.QUOTE(kabyss87 @ Jul 20 2016, 11:53 PM) But generally, as a person without knowledge on how construction works, what kind of physical sign we should look for to determine whether a construction was slow/fast in progress? To judge whether a condominium project is on time or not maybe one can calculate is such a way,i'm only determine the progress looking at the rate they built up the floors.. please enlighten.. From the SPA VP date, minus 4 month for getting CCC after CPC, then minus 8 months for general architectural works. Then use this date minus current date, this will be your total month to carry out the structural works. Then use this period divide by total story of your condominium, that will let you judge how many days in average are needed per floor in order to deliver the project on time. But some floor will take longer time to complete, such as the podium, 1st typical floor, transfer floor, non typical floor and etc. Hope this help. |
|
|
Jul 25 2016, 10:36 AM
Return to original view | Post
#4
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,510 posts Joined: Jan 2003 From: Atlanta |
QUOTE(xproc @ Jul 23 2016, 06:33 PM) i been told some projects can goes as fast as average 4 days per floor, Fastest i heard before is 6 days in average. 4 days maybe happened once in a blue moon.maybe they during concrete setting time they can do all the rebar and formwork installation for upper floor... QUOTE(WahBiang @ Jul 23 2016, 07:34 PM) From my previous study China those super highrise (above 70 storey), they can achieve 3 days circle in average. Center core is reinforced concrete while others are steel structure with bondeck. |
| Change to: | 0.0453sec
1.07
8 queries
GZIP Disabled
Time is now: 28th November 2025 - 07:07 PM |