 Construction Progress for High Rise Property, Average speed to complete one floor

For high rise property (such as condo and service apartment, upon completion of piling and other ground works, what is the average speed to complete for one floor? Be it car park level or residential floor.
 
Less than 1 week, 1 <= t [ 5 ] ** [41.67%]
Within 1-2 weeks, 1 < t <= 2 [ 2 ] ** [16.67%]
Within 2-3 weeks, 2 < t <= 3 [ 3 ] ** [25.00%]
Within 3-4 weeks, 3 < t <= 4 [ 1 ] ** [8.33%]
More than 4 weeks, t > 4 [ 1 ] ** [8.33%]
Total Votes: 12
Guests cannot vote 
views
     
TSWahBiang
post Jul 10 2016, 10:51 PM, updated 10y ago

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
Cast your vote and your comments, let's see the average speed in the construction industry for high rise...
TSWahBiang
post Jul 13 2016, 08:17 AM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
No vote?
TSWahBiang
post Jul 15 2016, 12:35 PM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
QUOTE(enriquelee @ Jul 15 2016, 10:27 AM)
It depends on many factors.
*
Factors such as? Say they need complete by 48 months?
TSWahBiang
post Jul 23 2016, 07:34 PM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
QUOTE(enriquelee @ Jul 21 2016, 10:46 AM)
Aluminium formwork usually take around 7 days circle per floor for typical floor.
To judge whether a condominium project is on time or not maybe one can calculate is such a way,

From the SPA VP date, minus 4 month for getting CCC after CPC, then minus 8 months for general architectural works.

Then use this date minus current date, this will be your total month to carry out the structural works. Then use this period divide by total story of your condominium, that will let you judge how many days in average are needed per floor in order to deliver the project on time.

But some floor will take longer time to complete, such as the podium, 1st typical floor, transfer floor, non typical floor and etc.

Hope this help.
*
I got the same thought. Say 48 months in SPA for 36 storey, 12months for painting, facilities, architechures and etc. Left 1 month per floor.. haha

QUOTE(xproc @ Jul 23 2016, 06:33 PM)
i been told some projects can goes as fast as average 4 days per floor,

maybe they during concrete setting time they can do all the  rebar and formwork installation for upper floor...
*
Thats fast till scary.. but if compared wih China, thats nothing..
TSWahBiang
post Jul 24 2016, 06:47 PM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
QUOTE(xproc @ Jul 24 2016, 02:27 PM)
those in china you mean precast system? sure fast lor.... but malaysia not cost efficient yet ler...
*
Not sure what it called, but I noe is damn fast.. their planning take a lot of time, but construction time is very short..
TSWahBiang
post Aug 3 2016, 12:07 PM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
QUOTE(kochin @ Aug 3 2016, 11:51 AM)
have done 4 days cycle for approx 17k sf floor plate previously.
shear walls all around no less and no brickwalls.

but not every floor also achieve 4 days cycle lah.
*
Actually, how to differentiate all these type of walls and its pros n cons?
TSWahBiang
post Aug 3 2016, 12:11 PM

Look at all my stars!!
*******
Senior Member
3,718 posts

Joined: Nov 2015
QUOTE(kochin @ Aug 3 2016, 12:09 PM)
mr. google is your best friend.
*
Tried but not much good info..

 