Did anyone has any experience is applying reno approval in Majlis Perbandaran Klang in recent year?
Can share some of experience on it?
Thanks ....
Appreciate a lots........
MPK Renovation Approval
MPK Renovation Approval
|
Feb 24 2016, 12:38 PM, updated 9y ago
Show posts by this member only | Post
#1
|
Junior Member
18 posts Joined: Feb 2016 |
Hi Anyone,
Did anyone has any experience is applying reno approval in Majlis Perbandaran Klang in recent year? Can share some of experience on it? Thanks .... Appreciate a lots........ |
|
|
|
Feb 24 2016, 04:33 PM
Show posts by this member only | Post
#2
|
Junior Member
50 posts Joined: Jan 2003 |
Starting my reno soon too.. input on such would be valuable.
BTW, if there are no extension done (most major is covering up a void in the car porch roof) need apply for permit? |
|
Feb 25 2016, 11:39 AM
Show posts by this member only | Post
#3
|
Junior Member
18 posts Joined: Feb 2016 |
|
|
Feb 25 2016, 12:43 PM
Show posts by this member only | Post
#4
|
Junior Member
352 posts Joined: Oct 2010 |
I applied initially to MPK for renovation via submission of new BP. Ended up it was put on hold due to changing from 1 storey to double storey, so a KM/DO is required that took me additional 5 months.
Renovation submission or BP is quite fast, if every supporting letter is in place, it would be approved within 1 week. Cheers |
|
Feb 26 2016, 10:42 AM
Show posts by this member only | Post
#5
|
Junior Member
18 posts Joined: Feb 2016 |
QUOTE(93126668 @ Feb 25 2016, 12:43 PM) I applied initially to MPK for renovation via submission of new BP. Ended up it was put on hold due to changing from 1 storey to double storey, so a KM/DO is required that took me additional 5 months. Do you need to get consent from neighbours? and how much deposit do you pay for debris collection ?Renovation submission or BP is quite fast, if every supporting letter is in place, it would be approved within 1 week. Cheers |
|
Mar 1 2016, 12:39 PM
Show posts by this member only | Post
#6
|
Junior Member
352 posts Joined: Oct 2010 |
Yes there's a form to sign by all adjacent direct neighbors.
Debris collection You can check with the person in charge. |
|
Mar 2 2016, 01:14 PM
Show posts by this member only | Post
#7
|
Junior Member
18 posts Joined: Feb 2016 |
Thanks for your inputs. |
|
Mar 3 2016, 11:26 AM
Show posts by this member only | Post
#8
|
Junior Member
322 posts Joined: Nov 2006 |
You would required to get both of your neighbour on left and right to sign letter of consent. However if they are unwilling to do so, you can just write neighbour unwilling to cooperate.
For total, you would need to prepare RM1108 for the whole process. RM600 for Alam Flora RORO bin. RM508 for MPK approval and deposit. As far as i remember, the deposit is RM100. The above figure is if you are doing your renovation based on the guidelines/standard set by the MPK. This means that you are doing based on the plan on the book that you bought. |
|
|
|
Mar 3 2016, 01:50 PM
Show posts by this member only | Post
#9
|
Junior Member
18 posts Joined: Feb 2016 |
QUOTE(wister @ Mar 3 2016, 11:26 AM) You would required to get both of your neighbour on left and right to sign letter of consent. However if they are unwilling to do so, you can just write neighbour unwilling to cooperate. Thanks wister for your details inputs. that's very helpful ....For total, you would need to prepare RM1108 for the whole process. RM600 for Alam Flora RORO bin. RM508 for MPK approval and deposit. As far as i remember, the deposit is RM100. The above figure is if you are doing your renovation based on the guidelines/standard set by the MPK. This means that you are doing based on the plan on the book that you bought. |
|
Mar 3 2016, 02:10 PM
|
Junior Member
18 posts Joined: Feb 2016 |
Wister, may i know how long is the process to get approval from MPK?
|
|
Mar 8 2016, 04:39 PM
|
Junior Member
322 posts Joined: Nov 2006 |
For standard ones, the PIC will tell you to come back for the permit the next day. However to be safe, go back 2days later. It should be done.
For myself, i had submitted the application and the permit is ready 2days later. Try call before going to collect |
|
Mar 15 2016, 12:19 PM
|
Junior Member
18 posts Joined: Feb 2016 |
QUOTE(wister @ Mar 8 2016, 04:39 PM) For standard ones, the PIC will tell you to come back for the permit the next day. However to be safe, go back 2days later. It should be done. Thanks Wister , for your adviseFor myself, i had submitted the application and the permit is ready 2days later. Try call before going to collect |
|
Aug 26 2016, 10:41 AM
|
Senior Member
532 posts Joined: Nov 2004 |
QUOTE(wister @ Mar 8 2016, 04:39 PM) For standard ones, the PIC will tell you to come back for the permit the next day. However to be safe, go back 2days later. It should be done. hi ,For myself, i had submitted the application and the permit is ready 2days later. Try call before going to collect Standard ones mean? if extend kitchen does it falls under standard? |
|
Sep 8 2016, 03:01 PM
|
Junior Member
322 posts Joined: Nov 2006 |
They will provide a guide book with standard renovations plan. There is 2 type of backyard extension, if you select to follow those drawing, then it should be fast and standard.
Non standard is you wanting to do something special and requires to submit your own architect drawing. this might take abit more time. |
|
|
|
Mar 29 2017, 02:06 PM
|
Junior Member
49 posts Joined: Jun 2011 |
QUOTE(93126668 @ Feb 25 2016, 12:43 PM) I applied initially to MPK for renovation via submission of new BP. Ended up it was put on hold due to changing from 1 storey to double storey, so a KM/DO is required that took me additional 5 months. Which dept in MPK I should visit to apply or submit the renovation plan?Renovation submission or BP is quite fast, if every supporting letter is in place, it would be approved within 1 week. Cheers |
|
Mar 29 2017, 04:02 PM
|
Junior Member
786 posts Joined: Sep 2013 From: Selangor |
|
|
Mar 29 2017, 04:53 PM
|
Junior Member
49 posts Joined: Jun 2011 |
|
|
Feb 27 2022, 06:04 PM
|
Junior Member
240 posts Joined: Aug 2011 |
Any idea if they only accept cash or can use credit card?
|
|
Aug 1 2022, 07:36 AM
|
Junior Member
14 posts Joined: Feb 2007 |
hai..may i know if i apply permit with mpk,will they come site visit to check the progress or not?
thanks |