Good thread. I produce my own defect report to submit to developer 1wk after the key handing over. Since I'm also in construction industry, I check defects in more details. Wonder if ppl would engage ppl like me to check defects -lol...
furryfluffy
post Dec 3 2010, 07:09 PM

Pass That Exam!
******
Senior Member
1,375 posts

Joined: May 2010


QUOTE(mohag @ Nov 25 2010, 04:35 PM)
Hi, just wondering, do you mean you provide services to check for defect?  And does this type of services exist in our shores? icon_rolleyes.gif
*
I am in the construction industry. My first project during my intership was to supervise my director's own bungalow & i followed my GM to the bungalow everyday to check defects.

Then I was assigned with medium cost condominiums & later exclusive condominium projects (both well known but i'm not advertising whistling.gif )

So I know defects quite well tongue.gif

I do not provide this service as a business... but wonder if i can do this part time... laugh.gif

I produce my own report for both property that I bought. However, I believe anyone can do it... like this thread is quite informative on checking defects nod.gif
furryfluffy
post Dec 19 2010, 03:55 AM

Pass That Exam!
******
Senior Member
1,375 posts

Joined: May 2010


QUOTE(Arkadeuz @ Dec 19 2010, 12:29 AM)
This is a very good thread
This question was asked way back earlier but I can't seem to find a direct answer (or maybe I've missed them, believe me.. I READ every post  sweat.gif ).  Could anyone please help RE-answer regarding this matter?  icon_question.gif

......and I would like to know if let say I submitted 20 or so list of defect but the developer only manage to rectify half of them and keep dragging, empty promises bla bla bla and so on.. WHEN can I write a letter to the stakeholder to hold the 5%? Should I asked them (in writing) to explain why the rest aren't fix first and give them grace period (again) or should I just sent the letter to the stakeholder?

Thanks notworthy.gif
*
If ur defects report has pic n had joint inspection with developer rep to acknowledge the defects, there will be less risks of dispute. Else any 3rd party (reno contractor) having worked in ur house, could be used to disclaim ur defects report. However, some developers r kind to rectify even if its after reno. Depends.

There is a timeframe to compleye the rectification. Check with ur developer. BTW, afaiac, retention sum only released upon completion of DLP.

 