NIce updates, Wet work should be pretty fast depends on the contractor, around 1 month plus if no delay. If you are installing security door , please note that the timing is crucial, must make sure the door is ready timely if not will delay your progress.
The rest also will take times , plumbing work (laying of new pipe)--> Elec (wiring trunking) --> installing Windows--> Tiles -->Grill -->plumbing (installing WC,water tap etc) -->Elec (installing downlight, fans, etc) --> paint
Major renovation (double story)