1. It states VP date is 2 November 2015 and Defect Liability Period ends 1 November 2017. Can developer states VP date 2 November 2015 when they only sent the letter dated 12 November 2015?
2. 10 November 2015 I went to have a look at the house. Of course, only from the outside. I could see marks they made to fix the imperfections in the house which still have not been fixed. Can they issue VP when the house still require fixing/repairs from developer?
3. There is this clause in the VP letter:
QUOTE
Please also take note that you shall deemed to have taken possession of the property (whether or not you actually have possession of the same) upon expiry of fourteen (14) days from the date hereof where after we shall not be liable for damages and losses to the property and/or to the fixtures and fitting therein.
Does this mean that 14 days after 12 November 2015, the developer are not liable for any defects, damages and missing fixtures and fittings?
4. The remainder owed to the developer is 20%. The last 5% is forwarded to the developer's solicitor. Will the last 5% will be paid automatically to the developer after 8 months and 24 months of VP as per the SNP? Let's say the developer doesn't perform all the defect liability, there is no stopping the last 5% payment?
5. Developer has apparently paid deposit for water and electric which they are asking us to pay before VP. Will I get a receipt from Syabas and TNB for the deposit? Also the deposit for TNB is RM1,210. Is this normal?
Thanks in advance.