Outline ·
[ Standard ] ·
Linear+
Investment EKOCHERAS @ JALAN CHERAS (V4) [MRT PROPERTY] [OT], Where Cheras becomes Mont'Jiulai
|
gks
|
May 8 2017, 05:32 PM
|
|
QUOTE(highburybaby @ May 8 2017, 05:01 PM) No wonder their tauke lost their bandar Malaysia...even small project like this also delay.... Being a fresh developer I think this case is more of underestimated scale involved in integrated development ie 3 storeys basement, malls and finally the serviced apartment/ soho/ office components. The time taken to complete the basement and ground works... it has taken Ekovest like 24months?
|
|
|
|
|
|
gks
|
May 27 2017, 04:06 PM
|
|
QUOTE(Alvelyn @ May 27 2017, 02:58 PM) Buyer deposit kept with lawyer. Buyer can choose any lawyer firm If abandoned, seller bear all the risk, safer than u buy from developer Forummer who does not understand, don't anyhow comment Why are you commenting on your own 2years ago post?
|
|
|
|
|
|
gks
|
Jun 5 2017, 08:49 AM
|
|
Commercial project from unproven developer.. read the SPA carefully... there are so many clauses will catch you. VP without CCC... billing upon work commencement ... GST ...etc etc It is not apple to apple comparison. Just because the Apple is cheaper you think it is better than Avocado. This post has been edited by gks: Jun 5 2017, 08:50 AM
|
|
|
|
|
|
gks
|
Oct 22 2017, 05:59 PM
|
|
It is foregone conclusion ekocheras will be delayed.
It is more of question Ekovest will be honourable to the SPA and pay out the LAD accordingly. Quoting example Sunrise was delayed in completing Arcoris to the tune of almost a year and no question asked to allocate funds to pay out full lad to the extend affecting their quarterly result.
|
|
|
|
|
|
gks
|
Oct 31 2017, 04:57 PM
|
|
QUOTE(BEANCOUNTER @ Oct 31 2017, 01:12 PM) reputable????? ekocheras is their first venture into property development leh wei reputable one is like UEM........delayed one year.....pay LAD in full no question asked. Not only paid in full.. but prior to the contractual delivery, Sunrise-UEM already sent out letter to purchasers inform them the delays and reiterate the commitment of their obligation. Ekovest? all the way until now the developer still insist can complete by end of this year.  And didn't address the concern by purchasers whether they still fulfill their obligation or not. This post has been edited by gks: Oct 31 2017, 05:00 PM
|
|
|
|
|
|
gks
|
Apr 30 2018, 02:35 PM
|
|
What is the physical progress now for ekocheras? Anyone mind to share?
|
|
|
|
|
|
gks
|
May 3 2018, 05:09 PM
|
|
QUOTE(tetsu @ May 3 2018, 03:19 PM) Any other hotel suite purchasers received a call from Ekovest for discussion? I thought the hotel block was pulled out from sale. Correct me if I am wrong.
|
|
|
|
|
|
gks
|
May 15 2018, 11:14 PM
|
|
QUOTE(Jagalat @ May 13 2018, 06:07 PM) Taken afternoon just now... BlkJ - Facility deck still in progress ... BlkH - L25 lower floor in progress ... BlkA(office) - Top floor/roof in progress ...  Thanks Jagalat kor. For block J & H if they are going to be VP-ed together... My gut feeling... another 8-9months at least.
|
|
|
|
|
|
gks
|
Jul 27 2018, 10:13 AM
|
|
QUOTE(planc @ Jul 21 2018, 08:04 PM) Which mall doing ok without cinema?  Publika Digital mall seksyen 13 Lowyat Sogo Sungei Wang Plaza The mall needs to find their own niche. Not all mall necessarily to be midvalley, oneU, pavilion, Sunway pyramid.
|
|
|
|
|
|
gks
|
Aug 3 2018, 03:05 PM
|
|
Target VP is Dec.2018 Attached thumbnail(s)
|
|
|
|
|
|
gks
|
Sep 13 2018, 12:00 AM
|
|
QUOTE(DesRed @ Sep 12 2018, 10:23 PM) I'm just observing here. To be fair, Tun M also engaged in a number of mega projects which doesn't really benefit the rakyat that much such as the creation of Putrajaya, KLCC, KLIA and Sepang. Not to mention Proton, and now a 3rd national car. Najib had TRX, Bandar Malaysia, Forest City, Trans Sabah gas pipeline, ECRL and HSR to name a few. Probably he (Najib) wants to become a more illustrious 'Bapa Permodenan' to outdo Tun M at the expense of the rakyat. The way I see it, both Najib and Tun M have their egos, no doubt about that, and trying to outdo each other. And since PH won, judging by the pace and brazenness shown by the latter by going head-on against many of the projects initiated by Najib, regardless of what stage of its construction, just proves this. I do not care any legacy projects by both however Jibby was caught pants down with corruption. Enough says...
|
|
|
|
|
|
gks
|
Sep 16 2018, 11:13 PM
|
|
QUOTE(BEANCOUNTER @ Sep 16 2018, 07:56 PM) Tq for yr effort all these yrs. In fact one yr extea work. Hope the lad will compensate u well. Cannot show off to my yii mah ku cheh jor in cny 2019....huhu... Looking at the progress... No way can vp end of this Year... Earliest possible is maybe after cny 2019... Hopefully ekovest learn their lesson well and in future has better planning for basement work.. This post has been edited by gks: Sep 16 2018, 11:16 PM
|
|
|
|
|
|
gks
|
Jan 5 2019, 06:53 PM
|
|
QUOTE(W.ROOK @ Dec 22 2018, 10:16 AM) Sometimes I wonder If the LAD claim can be higher than the property price itself  By theory yes however conventional wisdom will tell you that the project will be abandoned way before that...
|
|
|
|
|
|
gks
|
Jan 7 2019, 10:50 AM
|
|
QUOTE(BEANCOUNTER @ Jan 7 2019, 10:42 AM) taiko of all people I would assume you know that 2(H) [road serving to building] already completed jor. If they want to bill you they can actually. after 2(H) its vp time jor……… but bad timing lah…..CNY is around the corner, I wonder if they will serve you a big hong boa for cny or they rather wait after cny. but I was quite disappointing that the 2 big ticket items for the mall (supermarket and cinema) are no where to be opened whereas cny is less than one month away. Some development the mall not even ready yet after the residential completed like 2years For Ekocheras, I think they have done quite well, execution wise.
|
|
|
|
|
|
gks
|
Feb 13 2019, 08:00 PM
|
|
Raw design is not everyone cup of tea or coffee.
A lot of ppl they missed what is the bigger picture.
As property buyer I would rather have MRT station with elevated covered walkway just a short distant away. As property buyer i would rather have a vibrant retail at ground rather than "dead" retail for all the conveniences. If Ekovest going to pass the saving in the form cheaper rental rate to retailers to encourage them to open the shop earlier so that the retails can be occupied soonest possible. Retailers have stronger holding power as well while waiting for the footfall to build up. I would also rather have a VP on residential property where all components such as retails and office are completed at same time rather than in phases. I would also rather Ekovest honor the full LAD.
Then again, cannot stop anyone commenting about the raw concept. To be honest it is not my cup of tea as well however other matters are more pressing concern in my book.
This post has been edited by gks: Feb 13 2019, 08:05 PM
|
|
|
|
|
|
gks
|
Feb 13 2019, 09:44 PM
|
|
QUOTE(icemanfx @ Feb 13 2019, 09:31 PM) Those need to walk through "unfinished construction site" to reach home will certainly appreciate their well appointed home. Which project you refer to?
|
|
|
|
|
|
gks
|
May 27 2019, 08:58 AM
|
|
Each mall need to serve its own market... No point to compete with big four especially neighbourhood malls.
Bangsar Village, BSC are still surviving.
I noticed for EKC mall the f&b selection is quite unique particularly Chinese cuisine. I believe EKC mall management got it right there and not go for typical franchise f&b.
Only time will tell whether it is "new toilet effect" or the mall will be sustainable.
All the best!
This post has been edited by gks: May 27 2019, 08:59 AM
|
|
|
|
|
|
gks
|
May 27 2019, 12:04 PM
|
|
QUOTE(BEANCOUNTER @ May 27 2019, 11:22 AM) Its not the workmanship is not good....its just their raw and bare style are not yr taste..... Pls distinguish btw style and workmanshjp. Of all the so called 'malls' that opened in the past 1 to 2 yrs in klang valley, tis ekc considered riding in top already. Doesnt matter why carpark is full...at least there are footfall, restaurants are opening. Bear in mind tis is before their two main anchors, supermarket chain and cinema are opened. Tell tis to evolve mall, glo damansara n others they will be envy w bloody red eyes. The problem is many visitors compare footfall with big 5 (MV, oneU, Pyramid, pavilion and klcc).
|
|
|
|
|
|
gks
|
Sep 14 2019, 01:50 PM
|
|
QUOTE(9lai @ Sep 12 2019, 10:11 PM) Did u file complaint to developer and management office?
|
|
|
|
|
|
gks
|
Sep 23 2019, 01:58 PM
|
|
QUOTE(LiNKInPaRk108 @ Sep 22 2019, 11:58 PM) Broadly speaking, Sean has pointed many valid points (good and bad) about the development. Also worth to highlight comparison with rest of Cheras RM300-500K product is not apple to apple. Just like Sunway Velocity in Maluri, Tropicana Gardens in Kota Damansara, these development will be the market leader and command premium at the area. However.. the amount of incoming supplies surely bode well for the mall. Successful integrated development (TOD with mall, office, hotel, residential) will always be unique and given cost involved, unlikely developer going to build and sell at this price range anymore.
|
|
|
|
|