Tiny House Renovation Project, Sharing my reno journey
Tiny House Renovation Project, Sharing my reno journey
|
Oct 9 2015, 02:45 PM
|
Senior Member
3,020 posts Joined: Jan 2003 |
Cannot wait to see the unit after renovation.
|
|
|
|
Oct 15 2015, 11:11 AM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
reno on hold... the process for buying the unit takes about 4-6 months.. now stuck at consent pejabat tanah.
now im currently rent the unit and did some minor upgrade..picture coming soon |
|
Oct 15 2015, 01:13 PM
|
Senior Member
3,617 posts Joined: Oct 2010 |
|
|
Oct 15 2015, 01:21 PM
|
Senior Member
1,465 posts Joined: Sep 2008 |
|
|
Oct 15 2015, 02:36 PM
|
Junior Member
136 posts Joined: Jul 2008 |
@usop8290 wow! That took a while? Is it auction unit? May I know why it took so long?
My apartment is actually an auctioned unit too. 4th floor walk up, now I'm in process to acquire funds needed to pay for the unit lol! I did enter the unit last weekend tho, the roof has to be fixed. I'm a little worried about dealing with management, well, in for a penny in for a pound. Also got a quotation from a contractor about reno, can anyone tell me if it's resonable? New windows: 4 panels x3, 2 panels x1 Hacking n removing half wall Hacking n removing bathroom tiles walls Whole wall 1'x2' tiling bathroom New toilet That's all = RM8100 I think I have to deal with the roof first before proceeding with everything else. Will see if I can get other contractor out to give me a quote later.. |
|
Apr 29 2016, 11:44 AM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
Thanks for all feedback. Finally my reno works just started this week after all the purchase procedure is completed. it takes so long due to the slow lawyer work. mostly stuck at consent and now new rules on biometrik system at PTG Selangor.
This what i've been done in the last six months. mostly on painting and temporary carpet installation. All DIY. More renovation picture will be uploaded after this. stay tuned. |
|
Apr 29 2016, 11:51 AM
|
Senior Member
536 posts Joined: Aug 2009 From: Seri Kembangan |
good luck
|
|
Apr 29 2016, 11:55 AM
|
Senior Member
749 posts Joined: Apr 2008 |
QUOTE(usop8290 @ Apr 29 2016, 11:44 AM) Thanks for all feedback. Finally my reno works just started this week after all the purchase procedure is completed. it takes so long due to the slow lawyer work. mostly stuck at consent and now new rules on biometrik system at PTG Selangor. Bro your AC at the side of living room, thus where the compressor?This what i've been done in the last six months. mostly on painting and temporary carpet installation. All DIY. More renovation picture will be uploaded after this. stay tuned. |
|
|
|
Apr 29 2016, 11:56 AM
|
Senior Member
1,351 posts Joined: Jun 2009 |
that TV looks like mounted too high on the wall...
|
|
Apr 29 2016, 12:04 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
Want to share some item that i bought during homedec last year.
Granitech series sink and Le Celebrity water closet from bigbath Electrolux Chimney Hood EFC935SAR. after installation, it turn out that this hood is so big for my small kitchen. Total cost roughly around 4k includes small kitchen and bathroom accesories etc, tap,shower |
|
Apr 29 2016, 12:07 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
QUOTE(roxx @ Apr 29 2016, 11:55 AM) The compressor located outside at the balcony area. the wiring and piping is behind the beam. QUOTE(cedyy @ Apr 29 2016, 11:56 AM) it for safety purpose. otherwise my son will smash the tv if mount too low |
|
Apr 29 2016, 12:17 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
I was quoted RM6k for bathroom and kitchen renovation. The detail is describe below
Toilet: RM1500 (upah) + RM1500 (hack and install new tiles, new alu window, piping,painting,cement and etc) Kitchen: RM1500 (upah) + RM1500 (hack and install new tiles, built L-shape concrete table top, new sliding window, painting) |
|
Apr 29 2016, 01:13 PM
|
Senior Member
1,039 posts Joined: Aug 2013 |
Looking forward to seeing post reno pics!
|
|
Apr 29 2016, 02:38 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
Day #1 of the renovation..
-hacking old tiles,remove old piping, window and water closet. Day #2 -installing new tiles and window. water proofing the toilet Day #3 -build table top, install water closet. Sadly all the piping cannot be embedded into the wall due to limited budget and to avoid structural damage of the building. so all the piping will be visible. |
|
|
|
Apr 29 2016, 02:53 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
Bought some surface led downlight to replace kalimantan lamp and hanging lamp for dining area for the house at house of lighting puchong. cost about RM20-25 per pieces for the surface LED downlight and RM79 for the hanging lamp.
Forget to snap the real picture.however it is similar to this image. stay tuned for more updates |
|
Apr 29 2016, 03:59 PM
|
Junior Member
424 posts Joined: Mar 2011 From: Selangor |
I bought a flat at RM80k on 2012, spend around RM40k for all the renovation, i.e lay 2' x 2' floor tile all floor, re-do tiling at bathroom, ceiling, kitchen cabinet, tv cabinet, walk in wardrobe, study room, grille and etc.
some of friend and family always ask why I buy a flat instead of condo? But when they come to my house they will know the answer and I like the feel when they tell me "your house doesn't look like a flat!" |
|
May 5 2016, 01:14 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
Here are some updates
Day #4 Installing tiles for the table top, sink and stove Installing pipes, sink and bath accessories in toilet Day #5 Painting toilet and kitchen Replace old socket and install new lamps Day #6 Cleaning and preparing for laminate flooring |
|
May 5 2016, 01:15 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
QUOTE(jforjean @ Apr 29 2016, 03:59 PM) I bought a flat at RM80k on 2012, spend around RM40k for all the renovation, i.e lay 2' x 2' floor tile all floor, re-do tiling at bathroom, ceiling, kitchen cabinet, tv cabinet, walk in wardrobe, study room, grille and etc. yeah. i know that feel bro some of friend and family always ask why I buy a flat instead of condo? But when they come to my house they will know the answer and I like the feel when they tell me "your house doesn't look like a flat!" |
|
May 8 2016, 10:19 PM
|
Junior Member
424 posts Joined: Mar 2011 From: Selangor |
saw your bathroom's works. Since u have do re-tiling why don't concealed the water piping?
|
|
May 9 2016, 02:01 PM
|
Senior Member
998 posts Joined: May 2009 From: Bangi & Kuala Terengganu |
QUOTE(jforjean @ May 8 2016, 10:19 PM) money constraint Day #7 Renovation continues with the laminate flooring installation. The laminate floor was supplied and installed by Dynaloc. i was quoted RM4.70 psft including installation. Total cost for 5xx sqft about RM3500. Here are some photos The laminate floor design Installation process Final outcome |