QUOTE(tanseri @ Jun 2 2015, 11:55 PM)
How to move without basic infra. I thought ijm have satle all this issues. Or maybe they wait until phase 2 complete then only can have proper infra.
*
hmm.. at least 2 house has moved in + 1 renting. Street Light inside Chimes compound + around Rimbayu is working. Only the stretch from the traffic light towards the 3rd roundabout not working. But this is from my last visit 2/3 weeks ago not sure about now.

Inside Chimes the street light is working but it's still consider dark because all the houses the still no light.
hafizrahimi
post Jun 3 2015, 11:47 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(eastken @ Jun 3 2015, 08:48 AM)
you mean the kota kemuning 3rd roundabout? means is under MBSA?
*
Yep.. Kota Kemuning roundabout. Not sure under MBSA or MDKL..
hafizrahimi
post Jul 8 2015, 10:39 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(botack @ Jul 7 2015, 09:47 AM)
sorry, could not make it in time for the RA. sad.gif
*
When are you guys moving in? Seem like more people moving in after raya/year end. Some said will move in before CNY next year.
hafizrahimi
post Jul 8 2015, 03:39 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(botack @ Jul 8 2015, 10:53 AM)
going to wash my house this week since they have finally completed the rectification work, aircon install will be this week too. After raya moving in.. thumbup.gif

I don't think my row will have anybody moving in anytime soon. It seems deserted back there.  laugh.gif
*
eh.. last row which side? 24x75 got 1 already move in.. one soon and another one will start renovation soon.
hafizrahimi
post Jul 8 2015, 03:43 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(Hashima_fk @ Jul 8 2015, 12:36 PM)
Rectification work took so long since March only now completed? Oh no, I have told my owner moving end of Sept. Don't know if my unit in phase 2 has issue will be able to rectified by end of Sept or not
*
I would advice you to have back up plan because not sure you will be among which batch to receive the key. Once you got the keys then should be quite easy. Like me I thought I will get the keys in March but only got it in April and like Botack only got it in May.

One of Chimes owner I spoke to just move in few days ago while his unit undergo renovation. He just completed his master bedroom first and moved in. Reason being, he already sold his old house and have to move out after 3 month delay smile.gif
hafizrahimi
post Jul 8 2015, 03:55 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(spydermind @ Jul 8 2015, 11:20 AM)
Please share the quality of the workmanship ...highly appreicate
*
For my unit.. I think it was quite good. I don't have much complaint (still 2 pages long) but mostly are minor defect, hairline crack, paint issue, some minor dent etc. Only major issue with me is the low water pressure for cold water. Other units also have problem with mater pressure I think.

So far only one unit got major issue with water leakage but it could be due to the renovation that the owner did also. The leakage was rectified by IJM & owner's contractor.

In overall, I think the quality is quite good.
hafizrahimi
post Aug 10 2015, 11:44 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
I thought this issue already resolved. Last time it took a few weeks after VP to get all units installed with water meter and TNB meter. If not mistaken they said contractor don't have enough meter and what not. But after that all ok.
hafizrahimi
post Sep 29 2015, 11:04 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(blahbleh @ Sep 25 2015, 12:52 PM)
Has anybody moved in and can you share your story during night time, about the lighting around the area, access road and security personnels patrolling the area?
*
I've moved in and the only one in my lorong. Only a few days ago my front door neighbor move in. The road to Rimbayu from 3rd roundabout is properly light maybe just a small stretch that the light was turn off but still ok for me. The whole road in Rimbayu is with street light so that ok too.

Security. At night at the first guard near traffic light the guard will stop you and check your sticker. Then the guard to housing area will again check the sticker before letting you in. There are guards position at each corner of the Taman(I think.. didn't check all but seem like it. 4 corners 4 station with payung and table). Guard will patrol the area every half an hour or so.. some I saw on foot, some on bicycle and motorcycle. I saw them patrolling my backlane too. Not sure the other backlane.

Makan? Kota Kemuning the nearest loh.. Access road can use the Jalan Lombong to Cyber/Putrajaya or if you use 4WD just use the new connecting road with Saujana Putra.
hafizrahimi
post Oct 16 2015, 11:09 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(zzzhhhzzz @ Oct 15 2015, 08:44 PM)
There will be multiple entry point in the future... You can look at their master plan...there will be three roundabout into rimbayu from Kota kemuning side... One current one, another one through the center for flora and fauna and another at the other end of fauna..
*
plus there will be entry from Saujana Putra (in progress) and direct from SKVE from end of Fauna side but this will be in future la.
hafizrahimi
post Oct 16 2015, 11:13 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
new signage with all three developer. sign of more collaboration to come?


Attached thumbnail(s)
Attached Image
hafizrahimi
post Oct 16 2015, 05:39 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(eastken @ Oct 16 2015, 04:15 PM)
hafizrahimi, can i use your photo post in fb group? smile.gif
*
sure..
hafizrahimi
post Oct 20 2015, 04:32 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(blahbleh @ Oct 20 2015, 04:02 PM)
I sent an email to them. This is the response that I got:
----------------------------------------------------------------------------
Dear Mr. xxxxxxxx,

Thank you for your enquiry, we are currently working closely with the Bandar Rimbayu Team and will be sending invitations to join, to all owners of Bandar Rimbayu in stages.

Should you require any assistance or further information, please do not hesitate to e-mail us.

Once again, Thank You for your enquiry.

#togethergather #graaabthebetterlife
*
Rimbayu is currently working on a community apps where they share new info, promotion etc that could benefit the community. Was told they will launch the apps soon.
hafizrahimi
post Nov 13 2015, 03:50 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(halo5 @ Nov 13 2015, 03:43 PM)
Not thinking of selling at the moment.

Was planning to rent out my apartment per head and get extra RM1000 monthly.

Want to use that money to support my Penduline/Chimes monthly installment (if I decided to buy).
*
If for own stay I think better look for Chimes but I might be bias.. hahaha
hafizrahimi
post Nov 13 2015, 03:52 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
The construction for Chimes Fencing has started. Guard house also near completion.

This post has been edited by hafizrahimi: Nov 13 2015, 03:56 PM


Attached thumbnail(s)
Attached Image Attached Image Attached Image Attached Image
hafizrahimi
post Nov 19 2015, 02:14 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(lswei2003 @ Nov 19 2015, 12:39 PM)
Dear All Sifu, BR got any flood issue since last few days heavy rain??? just wondering.......
*
i've moved in. No flood whatsoever smile.gif
hafizrahimi
post Feb 9 2016, 06:09 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
Periwinkle progress as of today

This post has been edited by hafizrahimi: Feb 9 2016, 06:18 PM


Attached thumbnail(s)
Attached Image Attached Image Attached Image
hafizrahimi
post Apr 20 2016, 09:34 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(MusicForLife @ Apr 16 2016, 05:25 PM)
Wow, that's so fast! You checked with lawyer? Not your banker ah?

RHB very fast!

I am taking HLB btw.
*
RHB very fast because IJM's so called account also with them. So they just do internal transfer or something like that. Last time my loan disbursement also very fast.
hafizrahimi
post May 3 2016, 08:33 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(belfong @ May 1 2016, 06:10 PM)
Surprisingly there's not much complain about Chimes. I must say Chimes have really good workmanship.
*
Chimes also got their fair share of defects from simple and not so simple defects but everyone work together with the RA and approach IJM for rectification and some upgrades. So far everything is good.
hafizrahimi
post May 3 2016, 08:37 AM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(Mr.Swee @ Apr 30 2016, 11:10 AM)
First phase 22x70 selling sub sale rm650k - rm600k. And no ppl live there ??? So many signage for "FOR SALE" . Scare to live there since no ppl,staying there .

So which 1 should I go for ??? My budget is around rm850k

Penduline or phase 1 subsale ? Pls advice all master here ? I heard BAYAN from Tropicana give 10% rebate no downpayment. Is that true ?? Low entry or easy ownership package . What does that mean ?
*
If you want to move right away then Chimes la. So far the occupancy rate was about 10 - 15% but sure will increase in 1/2 years when the surrounding area mature a bit more (price will increase too). As for security, so far no incidents happen in Chimes and the perimeter fencing has been completed. Boom gate with access card are coming up really soon.
hafizrahimi
post May 4 2016, 02:50 PM

Getting Started
**
Junior Member
137 posts

Joined: Mar 2014
QUOTE(wlmak @ May 3 2016, 08:44 PM)
The Government of Malaysia has approved the appointment of turnkey contractor (Consortium IJMC-KEURO) and contractors for the West Coast Expressway (WCE).

Old news, but i do hope IJM will lobby for exit to Rimbayu
*
One of the exit is in Rimbayu (or you can say corner of Rimbayu). This project have really long story, canal city, WCE and all. IJM is the contractor for WCE surely the exit will be in the benefit of Rimbayu.

2 Pages  1 2 >Top
Topic ClosedOptions
 

Change to:
| Lo-Fi Version
0.0544sec    0.42    7 queries    GZIP Disabled
Time is now: 3rd December 2025 - 08:08 AM