Investment LIBERTY ARC @ AMPANG UKAY [OWNERS' THREAD], A massive 88-acre megaproject begins now

views
     
chongmelvin2238
post Aug 5 2016, 06:05 PM

On my way
****
Junior Member
539 posts

Joined: Apr 2012
anyone familiar with his dev... how's their workmanship? its a fully furnished unit and they said you will get what you see at the showroom. To construct show unit (false wall) is easier than actual building up brickwall .. Tiles arrangement may not be as good as you see at the show unit..

Can we reject or complain? Is this under Defect and Liabilities?

I came across a unit said with kitchen cabinets, wardrobe and etc.During SPA signing, it's not mentioned in the SPA but a separate letter stating that it's a freebies by dev. Worst is buyer have to handover the key back to developer after VP for 3 months for them to install the freebies.
chongmelvin2238
post Oct 28 2016, 11:21 AM

On my way
****
Junior Member
539 posts

Joined: Apr 2012
QUOTE(Fahmy mustaffa @ Oct 28 2016, 11:04 AM)
Seeking advise here...about tto sign spa...thenn the developer ask me to sign 1 letter...stated furnishing (i.d fitout and loose items) will be only complete 3mths after v.p date...any advise plz...
*
Meaning you have to pay for 3 months of instalment before you can rent it out of own stay. Assuming the SPA is 42 months, then you have to assume yours 42+3.
Question is what if they can't complete after 3 months?

 

Change to: