QUOTE(iwubpreve @ Dec 29 2015, 10:31 AM)
Thanks for the info. I am trying it out right now.Ask me anything abt Construction Industry!, Q&A
Ask me anything abt Construction Industry!, Q&A
|
|
Dec 29 2015, 10:55 AM
Show posts by this member only | IPv6 | Post
#861
|
![]()
Newbie
1 posts Joined: Jul 2015 |
|
|
|
|
|
|
Dec 29 2015, 11:07 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(zeist @ Nov 21 2015, 08:29 PM) iwubpreve depend on what kind of contract u enter. lump sum contract? or contract base on quantity constructed? contingency sum is for the sake of some budget to be buffer around in case additional cost require due to some issue that arise in future. provisional sum is due to the cost of work cannot be determine so they allow as provisional cost. in future the cost could be less or more than provisional cost. but better allow some instead of nothing right? the client thinking is always there have a cost in mind they don't wanna forecast wrongly. imagine u wanna sell a house to purchaser, u have to determine a selling cost right? if in future u need more cost to build, do u think u can change the selling price that u had sign S&P agreement with purchaser?- For a not so complicated/below RM1mil contract sum, is it true that by putting in provisional sum or contingency sum can affect the Final Account later on? - What kind of procurement is this? We as the design consultant but BQ was also prepared by us. We issue payment certification and certified on payments. We also appoint professionals BUT not main contractor. Owner did not engage a QS. As I know there are traditional, design and build and management contracting. Traditional = client engage consultant to design and engage contractor to build. design to come out first b4 contractor can bid the price. taken up time but cost is certain b4 construction start. Design and Build = client engage contractor to design and build. this mean contractor will engage consultant in this case, not by client. cost is uncertain. however depend on what kind of contract contractor enter, some competent contractor can give an agreed price and guaranty satisfy client by a conceptual idea given by client. that's the competency! contractor that get the job will start the work even the design not complete yet. design and construction do concurrently. Management Contracting = this is unusual here. reason is commercial issue. client always have a budget. but the cost cannot be determine b4 construction start. the cost only can be know part by part progressively and final cost only can be certain during final stage. QS is an option. not really require if the cost can be agree between client & contractor. |
|
|
Dec 29 2015, 11:22 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(Vk21 @ Nov 27 2015, 01:40 AM) Hi TS iwubpreve, 1. depend on what the client want. got plenty of land, build landed, got no much land, build high rise. beside that also see if the developer is target which market. with garage mostly is rich pipu, no?First, thank you for generously sharing your knowledge. I have some questions for personal inquiries: Edited, simplify question for less hassle in answering: 1. What are the decision factors for architect / landscape planner to select which house model to build, given Area? ( e.g. Hse Model A: single garage, 3 storey, Hse Model B: double garage, 2 storey, etc ) 2. What do are the input output for "cost estimation software" mentioned in this thread earlier, if you use excel, what are the input/output on the excel? 3. What are the considerations to make most profitable landscape plan? Old question: » Click to show Spoiler - click again to hide... « 2. excel is just a spreadsheet. just table out the item require and price it. like u need Qty x Unit Rate = Amount. example 3m3 concrete x RM300 = RM900 3. want to be profitable? just use pearl grass / cow grass. cheap and green |
|
|
Dec 29 2015, 11:24 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(ellenPAGE @ Dec 19 2015, 11:25 AM) Hi, All, good brick need furnace to burn, clay brick. so, no thanks. don't really need cement sand brick.Anyone interested in brick machine, can have a view of this site for clay brick machine, concrete brick machine, interlocking brick machine, concrete brick machine. http://www.block-making-machine.org/??id=yd |
|
|
Dec 29 2015, 11:30 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(jolipoli81 @ Dec 22 2015, 10:25 AM) A little technical and on the engineering side. go weight urself? gauge 22 (0.644mm) is bigger than gauge 28 (0.321mm). curi ayam?So my architect requested us to use Gauge 22 Exmet for the bricklaying. Contract stated weight not less than 1.2kg/m2 for light plaster, 1.6kg/m2 for plaster and 1.9kg/m2 for external rendering. Now the questions is, what gauge is 1.2kg/m2? Attach is the photo of the exmet we commonly used, Gauge 28, which is much lighter and thinner. ![]() |
|
|
Dec 29 2015, 11:43 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(OptimusStar @ Dec 23 2015, 03:52 PM) Hi, small hole? use those sealant that is paintable 1.I want to know all those drilling done when installing fitting what is the best way to cover them back to how it is before the drilling is done? Plaster doesnt seem well. I have a wall cracked slightly due to this, can we cement it back ? |
|
|
|
|
|
Dec 29 2015, 11:50 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
|
|
|
Dec 30 2015, 07:51 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
|
|
|
Dec 30 2015, 09:10 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(~HL~ @ Dec 30 2015, 08:37 AM) Huh got difference one ? depend which level u want to be in. there are many party 1.Sorry I'm newbie student only now Just wanna know how contractors make money and where do they get the capital ? Got what type of trades ? main contractor don't have much capital. they just hire a management team, they have probably some cash flow capacity, then they hire subcontractors do the work for them. client pay main contractor, then main contractor pay subcontractor. main contractor just earn abt 5% profit only. example client pay main contractor 155, so RM50 goes to expenses and overhead main contractor incurred, RM100 go to subcontractor, RM5 is profit. generally main contractor is a middle man that don't have any labour and material but still can delivery a building and making money. just like uber is a taxi company that didn't own any vehicle and they don't fetch passenger personally and yet still making money. just like airbnb is a house renting company that didn't own any houses hence they no property to rent yet still making money. just like alibaba is a company selling goods online yet they didn't own any goods and still making good money. |
|
|
Dec 31 2015, 01:38 AM
|
![]() ![]()
Junior Member
262 posts Joined: Feb 2011 From: bolehLAND! <3 |
Just want to know, those modular houses do they need building permit etc?
|
|
|
Dec 31 2015, 09:25 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,537 posts Joined: Jul 2008 |
if my concrete mix arrive after 2 hours batching time
leaving me with 30 minutes to place it do i still have to pay for the remaining concrete which i can not place in time ? |
|
|
Dec 31 2015, 09:32 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
|
|
|
Dec 31 2015, 09:36 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(Pewufod @ Dec 31 2015, 09:25 AM) if my concrete mix arrive after 2 hours batching time check the contract u have with the supplier. u can reject the concrete if it mention from batching plant to receiving is more than the allowance in contract. leaving me with 30 minutes to place it do i still have to pay for the remaining concrete which i can not place in time ? beside that u didn't carry out slump test? it will probably fail as the workability couldn't achieve |
|
|
|
|
|
Dec 31 2015, 09:43 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,537 posts Joined: Jul 2008 |
QUOTE(iwubpreve @ Dec 31 2015, 09:36 AM) check the contract u have with the supplier. u can reject the concrete if it mention from batching plant to receiving is more than the allowance in contract. what if its on per order basis and thus no contract formed ?beside that u didn't carry out slump test? it will probably fail as the workability couldn't achieve if the truck arrives after 2 hours batching time and we consider 1 hour of actual use time and the concrete workability to still stand during the whole 3 hours but no matter how we cannot finish all the concrete mix that we have ordered before it loses its designed slump thus we have remaining left how do we go about this ? |
|
|
Dec 31 2015, 09:55 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
QUOTE(Pewufod @ Dec 31 2015, 09:43 AM) what if its on per order basis and thus no contract formed ? that's why u have to be careful when u order concrete. tell them ur requirement. I believe ur project also got spec. for concrete right? eg. if the concrete spec. require is 30 minutes for concrete to be mix (in batching plant) and completion of placing at site. for pump mix is 2 hours, then u have to tell the concrete supplier to comply at beginning.if the truck arrives after 2 hours batching time and we consider 1 hour of actual use time and the concrete workability to still stand during the whole 3 hours but no matter how we cannot finish all the concrete mix that we have ordered before it loses its designed slump thus we have remaining left how do we go about this ? if the clerk of work is competent, he see the delivery of concrete already take 2 hours, he will reject and not allow u use that concrete. |
|
|
Dec 31 2015, 10:00 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,537 posts Joined: Jul 2008 |
QUOTE(iwubpreve @ Dec 31 2015, 09:55 AM) that's why u have to be careful when u order concrete. tell them ur requirement. I believe ur project also got spec. for concrete right? eg. if the concrete spec. require is 30 minutes for concrete to be mix (in batching plant) and completion of placing at site. for pump mix is 2 hours, then u have to tell the concrete supplier to comply at beginning. aihif the clerk of work is competent, he see the delivery of concrete already take 2 hours, he will reject and not allow u use that concrete. project at place where delivery is an issue and thus sometimes the delivery time is very hard to predict |
|
|
Dec 31 2015, 10:31 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
|
|
|
Dec 31 2015, 10:41 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,537 posts Joined: Jul 2008 |
|
|
|
Dec 31 2015, 11:49 AM
|
![]()
Newbie
1 posts Joined: Dec 2015 |
QUOTE(pijaklu @ Oct 17 2014, 02:52 PM) Recent fuel hike just kicked in for another 10% increase. Will the manufacturer and supplier increase their construction material selling price? Is the main contractor and sub contractor also demanding certain compensation due to this fuel hike? come to think of it why would any construction material increases when fuel price is increasing? |
|
|
Dec 31 2015, 12:40 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,829 posts Joined: Mar 2013 |
|
| Change to: | 0.0278sec
0.36
6 queries
GZIP Disabled
Time is now: 2nd December 2025 - 11:41 AM |