Finally I have SACKED Johnnie23 Be My Contractor, Strongly Not Recommanded ! At Own Risk!
|
TSannmix
|
Jun 30 2013, 05:05 PM, updated 13y ago
|
Getting Started

|
Update 30/9
This guy is not even a contractor, he is jus talking jobs and sub to some other contractor to do .. And always late payment to his sub contractor so yr job will be delay and delay
Then various excused will be given for the delay ( as another forumer mentioned before)
My house started renovation 3rd July, schedule completed date 26 July , nah... if i still wait for him i guess maybe december also canot finished. Finally sacked him and find own kitchen contractor to complete my kitchen cabinet , and go direct to the sub contractor En Aizad , to finished my tiling n touch up. and its finally done yesterday 30/9/2013, tats almost 3 months of nighrmare
So conclusion - NOT RECOMMANDED ! Boo... Learned my lesson
Name - Hafizan Lowyat id - Jonnie23 (012-9999104) company - Tareq Industries
If u guys still want to get cheap contractor, U can find direct that sub contractor guy. He is more experience and is a real contractor, but of coz, u still need to be there supervising his worker job coz some worker are abit lazy
Contact - En Aizad ( 0196368196)
For kitchen Cabinet U can contact - Mr Lim ( 0163021007 ) - recommanded
---------------------------------------------------------------------------------------------------------------------------------------------------------------------
Hi All
After researching for quite sometime (already tired) , finally have decided to engaged forumer Johnnie23 (Afizan) to handle my 850 sqf renovation.
Getting a quatation and site vsit with him is hassel free, prompt reply and on time for appointment , price are resonable too
Just paid 30% deposit upon confirming the job will be starting on next Tuesday, hopefully everything will goes well...
will update soon..
This post has been edited by annmix: Oct 1 2013, 11:56 AM
|
|
|
|
|
|
TSannmix
|
Jul 3 2013, 09:29 PM
|
Getting Started

|
QUOTE(TTCHIN @ Jul 1 2013, 11:29 PM) wow, your hse must be big big one, can afford 8k just for designing.  wah ya lo.. i think very big house and huge budget... my project jus like ikan bilis saje and keep budgeting too tight
|
|
|
|
|
|
TSannmix
|
Jul 3 2013, 11:23 PM
|
Getting Started

|
QUOTE(~Curious~ @ Jul 3 2013, 11:10 PM) i thinkk u shud have actually seen d drawing b4 hacking..like my hse,started hacking n building b4 giving proper thought then in d end tak suka then hack n rebuild,waste alot of money n time plus ppl annoyed lol Yea I know but in my case I already very firm tat I wanna hack the dining n kitchen wall so my apt will look bigger. drawing tat I wanna see is kitchen n toilet lo. Coz dun hv budget to do fancy fancy designs
|
|
|
|
|
|
TSannmix
|
Jul 3 2013, 11:25 PM
|
Getting Started

|
But my advise is.. pls see all the drawing before starting the work.. in my case I hv to take the risk coz need to start the reno asap...now jus hope afizan can do a good job for me ..
|
|
|
|
|
|
TSannmix
|
Jul 3 2013, 11:25 PM
|
Getting Started

|
But my advise is.. pls see all the drawing before starting the work.. in my case I hv to take the risk coz need to start the reno asap...now jus hope afizan can do a good job for me ..
|
|
|
|
|
|
TSannmix
|
Jul 30 2013, 09:42 PM
|
Getting Started

|
now i can say im totally unhappy and devasted with this renovation.. i learned a lesson !!
|
|
|
|
|
|
TSannmix
|
Jul 31 2013, 07:18 PM
|
Getting Started

|
Not abandon.. but delay of completion and some flaw n bad workmanship.. but hafizan insist I should comment only after he deliver the completion.. oh well now I will trust him again.. im not here to spoild someone rice bowl but I hope everything will be fine as insisted by him but I learned a lesson this time...
|
|
|
|
|
|
TSannmix
|
Aug 1 2013, 02:27 AM
|
Getting Started

|
Oh well now I jus hope the worker can complete by next week so I can move back asap.. coz cant afford to pay another 1month rent to my neigbour coz renting a room. fr her..Supposed completion by end july.. now I hv to beg neigbour to rent extra 1 week n not sure weather it will be completed on time or not.. I will post all the photos upon completion so everybody can judge of the workmanship n quality later
|
|
|
|
|
|
TSannmix
|
Aug 3 2013, 02:57 AM
|
Getting Started

|
Well.. it can be completed as schedule if the contractor allocate the same amount of worker to work on my site, coz he having another bigger project so only first week the progress is fast but from 2-3week, sometime only 2 person come to work and slow down the progress.. !
|
|
|
|
|
|
TSannmix
|
Aug 3 2013, 03:01 AM
|
Getting Started

|
QUOTE(annmix @ Aug 3 2013, 02:57 AM) Well.. it can be completed as schedule if the contractor allocate the same amount of worker to work on my site, coz he having another bigger project so only first week the progress is fast but from 2-3week, sometime only 2 person come to work and slow down the progress.. ! So for the past few days I try to go to the site as often as I can to check on the progress.. and really help speeding things up abit.. raya is coming soon, and hopefully as promised the flooring can be install so I can start moving back my stuff back..
|
|
|
|
|
|
TSannmix
|
Aug 4 2013, 06:45 PM
|
Getting Started

|
Yes no supervispor.. worker jus come and do thier work according verbally by the contractor and follow the marking by the contractor, for the past week I was on the site everyday to make sure all thing done properly as there was mistakes for the pass few weeks tat worker did not see the marking properly or jus confused of the work they are doin.. well I guess on my case.. im the supervisor la.. Now worker finished painting, but still 1 aircorn not installed and a exaust fan is missing in 1 toilet still not install.. been asking but say coming to install but never arrived. Payment already paid 2 weeks ago. Now painting done n later install will damage the wall n ceiling again I guess
|
|
|
|
|
|
TSannmix
|
Aug 5 2013, 07:38 PM
|
Getting Started

|
Latest update..Another bad news for me.
Flooring cannot be installed this week, only on 15th..Kitchen cabinet on 21th .. wondering why took so long as flooring I also paid full 2 weeks ago Also 80% contract price paid.. dont want to argue anymore becoz of Hari Raya..
|
|
|
|
|
|
TSannmix
|
Aug 5 2013, 10:18 PM
|
Getting Started

|
Lol. . My job is just ikan bilis only ard30-35k,
Well I need to go to check everyday sometime stay few hours at site for the past week, becoz if im away evetytime when im back i will find mistakes or flaws.
And I pay according to wat my contractor told 30% -then 50% n upon completion 20% (and also flooring, aircorn, lights all paid) . Tats why im quite upset I try to give him payment fast swhen he request so he can deliver my house but now I still hv yo wait at least 2weeks, mayb up to 4 weeks if promised is not fulfill again
|
|
|
|
|
|
TSannmix
|
Aug 6 2013, 12:15 AM
|
Getting Started

|
Yes im doin laminate flooring6 .. now schedule install laminate flooring on 15, then kitchen cabinet on 21 as been told
|
|
|
|
|
|
TSannmix
|
Aug 19 2013, 01:08 AM
|
Getting Started

|
Im still waiting the laminate flooring to be installed.. been reschedule a few time due to various reason by contractor.. everything is kinda stuck now..
|
|
|
|
|
|
TSannmix
|
Aug 20 2013, 04:52 PM
|
Getting Started

|
QUOTE(Axantas @ Aug 19 2013, 02:09 AM) The company that I engage is a construction company, not a contractor. These companies, they only involve in what they do only. In my case, they cover everything except carpentry. You are right, the quote that they gave are properly made. It has all the details including material used (brand, type and quantity), estimated date of completion (and a clause that states a maximum additional 10% liable to vary) and price in a complete agreement. I don't understand, laminated flooring should be something that could be arranged in a short time. Could you check if the contractor has made his payment or order? Sometimes, the contractor ran out of money. Talk to them. Make sure no payment is further made, but you can always tell your contractor to arrange and you will pay directly to these sub-contractor. Balance only to be paid to him. What matters is completion and handover. when he say he can handle the laminate flooring at first so i was like ok.. let him handle so he can cordinate , that was 1 month ago . so after that he ask me to pay full becoz he say supplier need full payment upon confirm the job.. ok.. well i was like fine.. i transfer full amount to him like 3 weeks ago.. then after that work delay , reschedule few times installation and never come, last week then told me the design i want no stock, so i have to choose another pattern which i am not really like, but i have no choice coz i cant stand the delay already, now he say tomorow will come and install , i hope the laminate flooring staff will come la
|
|
|
|
|
|
TSannmix
|
Aug 20 2013, 09:42 PM
|
Getting Started

|
QUOTE(Axantas @ Aug 20 2013, 05:26 PM) They use normal cement to fill the gap between tiles? Nowadays, most people use coloured grout, such as those by Davco. This is the problem when we engage contractor that are not up-to-date in design and material technology. i think maybe my job is on budget so its ok la.. im not complaining about normal cement if its property closed the gap wat im not really like is they put the plastic strip between the tiles and over the door frame site , when i saw it is too late cant remove anymore, they worker told me even 5 star hotel put like this , i was like.......speechless.. i only see these plastic strip on those budget hotels.. Attached thumbnail(s)
|
|
|
|
|
|
TSannmix
|
Aug 20 2013, 09:46 PM
|
Getting Started

|
QUOTE(sekkee @ Aug 20 2013, 07:11 PM) I think he took your money meant for laminated flooring to roll. And you don't need to pay 100% before they start work. I paid 70% only and gave them 4 days notice to start work and that is just after Raya. Work completed within 3 days for 1800 sq feet. Balance of 30% waiting for them to bill me - I called them and the said dont worry, they will bill me after their logistic tell them how exactly how much material was used. well i paid 30 % upon confirming the jobs, they started as schedule and after 3 weeks asked for 50% , so i paid accordingly.. but then after this everything slow down .. i try to pay him fast so he can complete my thing soonest possible but .......
|
|
|
|
|