QUOTE(naznee @ Jan 3 2014, 01:26 PM)
Just received the progressive billing for 10% construction completion
*
The first 10% for piling stage? Quite fast imho...even the much earlier launch SP Setia Dwiputra has yet to complete the piling stage~ sweat.gif sweat.gif
deed
post Jan 23 2014, 12:23 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(syiafuku @ Jan 20 2014, 11:48 PM)
yaw guys usually how fast did u have to sign the snp after booking? my friend said within 2 weeks is it true?
*
Between 2weeks to 1 month if Im not mistaken..
deed
post Mar 7 2014, 09:24 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Any update on this development? And how is Ayer@8 doing?
deed
post Jul 2 2014, 11:21 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


So is it comfirmed progress billing already reached 30%? Which block is that.
deed
post Jul 24 2014, 11:40 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(Blue_Blood @ Jul 11 2014, 12:27 AM)
Bro...this project also u sapu?wow
*
Bro r u stalking me~ shocking.gif tongue.gif tongue.gif

Hard to resist property at good location with positive prospect lah bro... brows.gif tongue.gif
deed
post Dec 29 2014, 04:03 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(rayzlan @ Dec 29 2014, 02:35 PM)
Does Aura is near Tamara Residence as well
*
Aura should be at the other side of Presint8, near Istana Selangor side...
deed
post Dec 30 2014, 11:05 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(phlegmon @ Dec 29 2014, 04:52 PM)
I'm not buying PJH property....price is so crazy..AURA project is about rm700/sqft!!

For investment not good but for ownstay i will recommend..the surounding area is nice...

But other project under projek sakit...
*
Apparently Aura Residence was advertised as exclusive low-density development by PJH...although the location is much more inferior than Tamara. Putrajaya property is actually good for both ownstay and investment as the infrastructure and landscaping is definitely impressive. It is not good for flipper though.

QUOTE(rayzlan @ Dec 29 2014, 05:14 PM)
wow 700/sqft .. I just look the tread Tamara is 400-500/sqft ..I thought Aura should increase by 20% the most .. Does anyone know any unit available for Tamara .. sent email to PJH no reply .. call the general line no one picking up the phone
*
If not mistaken Tamara already sold-out. It will be better to go personally to PJH Marketing Suite and check yourself if you are interested to purchase PJH property.
deed
post Jan 12 2015, 07:45 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(En_A @ Jan 11 2015, 10:46 PM)
Any news on this property? Projeck sakit means what? Bought one too but only got 10% completion letter so far block A. Does that means the completion estimated 2018?
*
Means that the development progress is behind schedule. If not mistaken the main contractor has already been changed by PJH to rectify this. The new contractor now catching-up with the construction.
deed
post Feb 18 2015, 04:34 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Tamara construction getting faster by days. Saw several tower cranes already operational at site~ Further up the road PJH is developing something by the lakeside..
deed
post Jul 23 2015, 10:18 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


How is tamara progressing so far? Just wonder if it can be completed on time. When did the First-Phase buyer S&P signed? hmm.gif hmm.gif
deed
post Jul 29 2015, 01:56 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(tangent88 @ Jul 23 2015, 07:45 PM)
Checked with PJH for sure will delay n promised will pay LAD according SnP.
*
What is the estimated delay time? Hopefully PJH dont cut-back on quality to compensate on delay. unsure.gif

QUOTE(goldputra @ Jul 26 2015, 11:06 PM)
Lets join up the community in FB.
*
Is it a group or just a community page? hmm.gif
deed
post Jul 31 2015, 03:28 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Its better PJH dont push the completion early as to make sure that contractor do not compromise on the workmanship. Rushing job is not good...
deed
post Aug 24 2015, 11:03 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Tamara construction seems on-track and well~ notworthy.gif notworthy.gif I supposed Ayer 8 businesses are also picking-up but guess it need more quality tenant/shops.

Similarly Dwiputra Residence by SP also progressing super fast.. shocking.gif
deed
post Oct 19 2015, 10:50 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Stage 2F means already 70% right? shocking.gif shocking.gif Wow very fast construction indeed~
deed
post Oct 23 2015, 11:04 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(goldputra @ Oct 23 2015, 05:38 PM)
Hai all. Any idea on how to push Bank Lawyer to advise bank to disburse as per billing? They are not answering call/whatapps.. need to push prior dateline otherwise kena interest masa ambil kunci.. headache this type of lawyer..
*
Lawyer can be a headache. Suggest that u follow-up with the bank instead...or the bank-rep which u applied the loan. Make them push the lawyer instead.
deed
post Nov 2 2015, 10:01 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(Krgoh @ Oct 24 2015, 12:09 PM)
Stage 2f but only 40% progress
*
Yeah billing 70% but construction looks like less than 50% from outside. Pjh confidence that it could be completed by next year though. Btw what is the earliest first-phase buyer s&p date?
deed
post Jan 3 2016, 11:38 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


Progress update.

Block C at top floor.
Block D reaching Level 20.

Attached Image Attached Image
deed
post Jan 8 2016, 02:47 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(goldputra @ Dec 27 2015, 05:33 PM)
One question, DIBS according to SPA 3 years is from Stamped SPA date right? Let see on June 13, 3 years is June 16. Anyone can share.
*
The earliest purchaser s&p was on June 2013?
deed
post Jan 10 2016, 09:59 AM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(skeimc @ Dec 24 2015, 11:46 PM)
No way can be completed by Jan 2016 as per their brochure.
*
QUOTE(goldputra @ Jan 8 2016, 05:53 PM)
Should be earlier. I bought mine 2nd Phase.
*
Perhaps first phase purchaser stamped on January then as per Pjh estimated completion.
If so can start counting LAD for each day delayed already~ brows.gif brows.gif
deed
post Jan 14 2016, 02:46 PM

Enthusiast
*****
Senior Member
833 posts

Joined: Dec 2004
From: K.L.


QUOTE(tangent88 @ Jan 10 2016, 01:29 PM)
1phase start selling in mac 2013 should be get SNP stamped around may or June. Any 1st phase buyer can confirm?
*
Oh in that case Pjh still have time to minimize compensation. Doubt that the project can be completed by middle of this year though. Nearby Fera semi-D also yet to VP though the houses were launched way earlier. In the mean time, hopefully Ayer@8 commercials will mature. Any prediction on the rental rate for Tamara? hmm.gif