http://cmcgruppo.com/blogit/2013/06/21/chl...tenza/untitled/TBM Chloe is ready to start digging.
Status of stations on DTL2.
Bukit Panjang - Casting the intermediate slabs of the station (around concourse level - B1).
Cashew - The station roof is done already.
Hillview - In process of pouring concrete for the station area.
Beauty World - In process of pouring concrete for the station area.
King Albert Park - Work stopped as contractor is bankrupt.
Sixth Avenue - Work stopped as contractor is bankrupt.
Tan Kah Kee - Work stopped as contractor is bankrupt.
Botanic Gardens - In process of pouring concrete for the station area.
Stevens - Excavation using top-down method is complete and should be pouring concrete for the final layer.
Newton - In process of pouring concrete for the station area.
Little India - The station roof is done already.
Rochor - Excavation under way.
The contractor for track works will be moving in to the Little India site soon to start work on laying tracks.