TBM progress update (won't be 100% accurate as it is based on periodic update by MRT Corp)

user posted image

SMT1 (Semantan 1) = covered 1264 m from Semantan portal, towards KL Sentral (as of 2nd December 2013)
SMT2 (Semantan 2) = covered 943 m from Semantan portal, towards KL Sentral (as of 2nd December 2013)
Inai 2 = covered first ring, towards Bukit Bintang Sentral station (as of 29th November 2013)
COC1 (Cochrane 1) = covered 900 m from Cochrane station site (as of 16th November 2013)
COC2 (Cochrane 2) = covered 600 m from Cochrane station site, towards Pasar Rakyat station (as of 16th November 2013)
MAL 1 (Maluri 1) = covered 163 m from Cochrane station site, towards Maluri (as of 16th November 2013)
MAL 2 (Maluri 2) = covered 38 m from Cochrane station site, towards Maluri (as of 16th November 2013)
*
notworthy.gif notworthy.gif

btw, kampung, how's LRT extension? i thinks we have forgets about LRT construction!
vin_ann
post Jan 11 2014, 06:56 PM

10k Club
********
All Stars
10,912 posts

Joined: Feb 2006
QUOTE(lilzany @ Jan 11 2014, 04:11 PM)
user posted image

From the looks of here, that means the predicted out was on the spot. This is some solid engineering calculations.
*
rclxms.gif rclxms.gif
vin_ann
post Aug 4 2014, 01:45 PM

10k Club
********
All Stars
10,912 posts

Joined: Feb 2006
Thanks Kampung for the updates!