QUOTE(tomjason @ Jul 30 2012, 04:16 PM)
hi bro,
sorry late reply..did not notice..
to remove pillar, cannot simply remove pillar dangerous must study the situation first..if possible..can upload pic..to see the situation..
TQ
Added on July 30, 2012, 4:28 pm
2) Break 1 wall at downstair room for kitchen extension (6ft x 9ft)
Ans: EC , 2 indon worker (RM180) , job one day, max 2 days, so total RM=180. Main contractor will mark up the price for untung.
3) Labour cost for retile, need to remove all the old tiles (downstair ground floor 20ft*65ft (all the land area), upstair ground floor (32ft x 20ft), tiles buy by myself.
Ans: EC, 20x65 ft. COst to remove = RM2,600. EC for retile (cost upah&cement etc ) tile owner buy RM=5200-RM6000.
hey tomjasonsorry late reply..did not notice..
to remove pillar, cannot simply remove pillar dangerous must study the situation first..if possible..can upload pic..to see the situation..
TQ
Added on July 30, 2012, 4:28 pm
2) Break 1 wall at downstair room for kitchen extension (6ft x 9ft)
Ans: EC , 2 indon worker (RM180) , job one day, max 2 days, so total RM=180. Main contractor will mark up the price for untung.
3) Labour cost for retile, need to remove all the old tiles (downstair ground floor 20ft*65ft (all the land area), upstair ground floor (32ft x 20ft), tiles buy by myself.
Ans: EC, 20x65 ft. COst to remove = RM2,600. EC for retile (cost upah&cement etc ) tile owner buy RM=5200-RM6000.
2) how do we get contacts for indon workers? I may have few walls to break down
3) in your opinion, do you think its advisable if we consider to do the tile removal ourselves? been researching a lot on tutorials on youtube. seems fairly straightforward to get it remove.
Cheers