QUOTE(West Wing @ Dec 20 2012, 05:43 PM)
Hi All Sifu,

I want to build a house on my land and the contractor quote me Rm1.2M and he told me that only the house and not even include piling and just today, he provided me with the piling quotation.

I want to ask Sifu here is the 7ins. Piling quotation below reasonable or not.

1. Mobilisation, installation and demobilisation og piling equipments Rm8,000
2. Setting out of piling points @ Rm8 x124= Rm744
3. 6m starter points @ Rm160x124= Rm19,840
4, 6 m  extentiong points @Rm172x124=Rm21,328
5.Handle, transport and pich @Rm10x248=Rm2480
6.Driving of 175mmx175mm r.c piles Rm8x1488= Rm11904
7.Extention joints(bult weld) to piles Rm20x124= Rm2480
8.Cut off piles head Rm28x123= Rm3472
9.PDA test on 1st.  Rm1750
10. PDA test on Subsequence   Rm 1200

Total Rm68,240 and I am surprised and can someone here enlighten me on the above....
*
item
1. high, normally <5k in klang valley for 1st rig, 3k for 2nd rig
2. reasonable
3&4 . normally started pile with shoe more expensive than extension pile +-rm10
5. reasonable
6. market rate
7. on high side, weld joint for 7" <rm15
8. cut off pile above ground or cut off after excavate for pilecap? request for diamond cutting after excavation..no double handling
9. PDA market rate 1st rm1200, subsequence rm800-1000 depend on nos


Added on December 25, 2012, 2:54 pm
QUOTE(ontrack builders @ Dec 24 2012, 04:55 PM)
If the engineer's plan said so then there's no argument there.I used to build an elevated water tank and we only need 60 something points.Your house must be very big then and your soil is soft hence the needs for numerous amount of piles point.

Other than the things I've mentioned the rate seemed reasonable enough for me.However please bear in mind,it's in provisional quantity meaning that the more they do the work,they more u'll have to pay.If the number of piles used reduce,then it will be below 68k and vice versa.

Cheers!
*
by looking at the quantities allowed, i doubt the soil is soft, 124 point and only allow 124 starter & 124 extension, meaning only max 12m per point, sometime the engineer just simply taruk as much point one doh.gif

This post has been edited by skng03: Dec 25 2012, 02:54 PM

 