Hi, Sifu smile.gif

I would like to renovate my old landed house (20ft x 65ft) with :

1) To extend kitchen (20ft x 10ft - 7ft x 5ft) with flat and horizontal concrete roof remark: My toilet (7ft x 5ft)at part of the 20ft x 10ft. I don’t want to move it, just maintain.
2) Break 1 wall at downstair room for kitchen extension (6ft x 9ft)
3) Labour cost for retile, need to remove all the old tiles (downstair ground floor 20ft*65ft (all the land area), upstair ground floor (32ft x 20ft), tiles buy by myself.
4) Remove wall old tiles and retile for 3 bathrooms, buy tile myself ( 3 x 8ft x 5ft x 9ft)
5) car poach remove 1 pilar at center and remove old roof,
6) build 2 pilar at side and flat and horizontal concrete roof ( 15ft x 20ft) for car poach
7) kitchen table top 21ft
8) change main door 3ft wide to 6ft wide.

Thanks is advance for your help notworthy.gif
iamsolucky
post Jul 30 2012, 05:47 PM

Getting Started
**
Junior Member
61 posts

Joined: Mar 2011
QUOTE(tomjason @ Jul 30 2012, 04:16 PM)
hi bro,

sorry late reply..did not notice..

to remove pillar, cannot simply remove pillar dangerous must study the situation first..if possible..can upload pic..to see the situation..

TQ


Added on July 30, 2012, 4:28 pm
hi bro,

below my ans:
1) To extend kitchen (20ft x 10ft - 7ft x 5ft) with flat and horizontal concrete roof remark: My toilet (7ft x 5ft)at part of the 20ft x 10ft. I don’t want to move it, just maintain.
Ans: estimated cost (EC) = RM20K
2) Break 1 wall at downstair room for kitchen extension (6ft x 9ft)
Ans: EC , 2 indon worker (RM180) , job one day, max 2 days, so total RM=180. Main contractor will mark up the price for untung.

3) Labour cost for retile, need to remove all the old tiles (downstair ground floor 20ft*65ft (all the land area), upstair ground floor (32ft x 20ft), tiles buy by myself.
Ans: EC, 20x65 ft. COst to remove = RM2,600. EC for retile (cost upah&cement etc ) tile owner buy RM=5200-RM6000.

4) Remove wall old tiles and retile for 3 bathrooms, buy tile myself ( 3 x 8ft x 5ft x 9ft)
Ans:I will you Cost to remove tile is RM2 sq ft. Cost to retile is RM4-Rm5 sq ft. Then you can mutiply.

5) car poach remove 1 pilar at center and remove old roof,
Ans: must need to see situation first. pillar cannot simply remove dangerous. upload the pic for me to estimated.

6) build 2 pilar at side and flat and horizontal concrete roof ( 15ft x 20ft) for car poach
Ans: EC RM8700-RM9000 include tile.

7) kitchen table top 21ft
Ans: EC=RM1260 not include tile.

8) change main door 3ft wide to 6ft wide.
Ans: wood frame expensive , depend on wood type. i will give you labor cost&material cement etc. RM 640-RM800.

-----------------------------------------------------------------------------------------------------------------------------------------------------

Tip:

There is tip how to have smooth plaster ceiling when painting. If want to know inform me.
TQ
*
Thank you very much for the info.
Please share with me about tip how to have smooth plaster ceiling when painting notworthy.gif

iamsolucky
post Aug 1 2012, 03:37 PM

Getting Started
**
Junior Member
61 posts

Joined: Mar 2011
QUOTE(tomjason @ Aug 1 2012, 09:51 AM)
hi bro,
well..this tip is very very simple but most contractor neglect it. It the choice of paint roller and most important is the sequence is painting..want detail PM me.


Added on August 1, 2012, 9:52 am
as my explained above.
*
Hi, Thank you very much for the tips again. I would like to know more details pls. notworthy.gif

Another questions,

for the wet work kitchen extension, Is it better to buy the material by ourself then just pay the labour cost to the contractor for the job? Under this condition we can use the better material (red brick, thicker metal, etc). If can, normally the material cost is how many percent of the total cost (material + labour) from the contractor?

Thanks

 