Renovation Secret & Tips Revealed, Secret&Tips contractor wont tell you
|
West Wing
|
Dec 20 2012, 05:43 PM
|
|
Hi All Sifu,
I want to build a house on my land and the contractor quote me Rm1.2M and he told me that only the house and not even include piling and just today, he provided me with the piling quotation.
I want to ask Sifu here is the 7ins. Piling quotation below reasonable or not.
1. Mobilisation, installation and demobilisation og piling equipments Rm8,000 2. Setting out of piling points @ Rm8 x124= Rm744 3. 6m starter points @ Rm160x124= Rm19,840 4, 6 m extentiong points @Rm172x124=Rm21,328 5.Handle, transport and pich @Rm10x248=Rm2480 6.Driving of 175mmx175mm r.c piles Rm8x1488= Rm11904 7.Extention joints(bult weld) to piles Rm20x124= Rm2480 8.Cut off piles head Rm28x123= Rm3472 9.PDA test on 1st. Rm1750 10. PDA test on Subsequence Rm 1200
Total Rm68,240 and I am surprised and can someone here enlighten me on the above....
This post has been edited by West Wing: Dec 20 2012, 05:47 PM
|
|
|
|
|
|
West Wing
|
Dec 23 2012, 08:06 PM
|
|
QUOTE(ontrack builders @ Dec 20 2012, 11:15 PM) Do u really need 124 points for the piling works?? That is quite a huge amount.Initial pile and extension pile should have been of the same rate.However the price to supply the piles (175mm x 175mm) is quite cheap.Usually people would quote handle,transport,pitch and drive as a same rate. Please ask your contractor whether this work will be remeasured as provisional quantity because if it is,then the amount of RM 68k isn't a fixed amount. Cheers! TQ for you reply. The numbers are as per Engineer's plan and all I need to know whether these are standardized or normal quote for piling. The contractor told me that it will be lesser if the requirement reduce but as a layman, I find it very expensive and what you think. Appreciate and thank again.
|
|
|
|
|
|
West Wing
|
Jan 2 2013, 11:01 AM
|
|
[quote=skng03,Dec 25 2012, 02:50 PM] item 1. high, normally <5k in klang valley for 1st rig, 3k for 2nd rig 2. reasonable 3&4 . normally started pile with shoe more expensive than extension pile +-rm10 5. reasonable 6. market rate 7. on high side, weld joint for 7" <rm15 8. cut off pile above ground or cut off after excavate for pilecap? request for diamond cutting after excavation..no double handling 9. PDA market rate 1st rm1200, subsequence rm800-1000 depend on nos
Added on December 25, 2012, 2:54 pm
Appreciated and TQ
|
|
|
|
|