Welcome Guest ( Log In | Register )

Outline · [ Standard ] · Linear+

 Reno Sequence, First House - Confuse with the reno seq

views
     
hellokitty82
post Feb 6 2012, 10:09 AM

Getting Started
**
Junior Member
272 posts

Joined: Sep 2006
From: malacca


QUOTE(adrianjc @ Feb 5 2012, 06:10 PM)
Sequence as follows:

Wetworks:
Basically means any extension or cement/concreting work. This is the absolute first thing to be done.

Electrical & plumbing:
Comes after wetworks or running concurrently towards tailend. This should include plaster ceiling lighting points. Plumbing is for any additional taps, inlets & outlets as required or installation of pump. Moving water main should be done at this point.

Plaster ceiling/Skim coating of walls:
Next in line for progress is installation of plaster ceiling as this can be messy. Skim coating of walls only if necessary or if budget allows.

Tiling:
After plaster ceiling is done in specific areas you can start tiling the toilets, kitchen or living hall.

Painting & door installation:
1st coat of paint for walls and plaster ceiling. If changing doors, these can start going in here. Door frames have to be installed before this point if being changed.

Installation of timber/laminate/engineered flooring:
With the glue and all being used, this flooring to be done last after aircond, lights, fans are installed.

Retiling porch, rebuilding gate pillars:
This is for finishing the outer part of your house. Basically the inside is more or less done. Installation of outdoor water filter.

2nd painting round:
Self explanatory.

Installation of built-ins:
Cupboards, kitchen cabinets, etc can be now installed. Tell supplier to not scratch your floor if using timber flooring.

Polishing of flooring (applicable for marble flooring only)

This is just a general guideline. Some of the items can be done to some extent overlapping with each other usually during tail end of each process. Time for each is dependant on your requirements. Hope that helps a lil.
*
thanks! this is very very useful to everyone who is first timer as well.

I also got my double storey 24''x90'' house key recently but yet to do anything. currently, the developer still touching up after our complaint letter submitted.

I also do not have idea which one to go first as we have limited budget. as we are not in hurry, so we plan to do it slowly.

so referring to your sequence.

is it alright if i start with my car porch and backyard first? i gotta to tiling for both car porch and backyard. no extension on car porch. this is wetworks as well? unsure.gif

as for the interior of the house, we will retain the original tiling. but maybe will be doing laminated flooring from the staircase up to first floor. I should start this first or electrical/plumbing first? unsure.gif

please advise.. notworthy.gif notworthy.gif



 

Change to:
| Lo-Fi Version
0.0191sec    0.62    6 queries    GZIP Disabled
Time is now: 19th December 2025 - 12:53 AM