1.Wiring (add power point etc) - electrician
2.Fans, air con, lightings - electrician
3.Splashback mosaic – cement worker
4.Paint – painters
5.Kitchen cabinet, hood, oven and hobs – KC supplier
5.Autogate – autogate contractor
6.Paint - painters
7.Wardrobes and furniture – add ons if still have money later
Which should be the better sequence so the cement workers and painters don’t have to come twice[COLOR=blue] to patch up the hackings?
If I put painting after aircons, lightings and kitchen were done will the painting work stain them?? But if I put the painters earlier before installing these stuffs, won’t they have to come back to touch up?
Autogate will be asking a friend to do, but he told me he don't know how to do the cement. So cement worker have to patch up later too.