i have got my quotation from a contractor, is the price reasonable or too high
below is the list
CODE
Item Job Description Unit Qty Rate Total
1 fan point no 2.00 55.00 110.00
2 lighting point no 17.00 45.00 765.00
3 13amp power point no 24.00 70.00 1,680.00
4 cooker point no 1.00 130.00 130.00
5 aircond point no 3.00 130.00 390.00
6 painting work (except door) sf 1,400.00 lump sum 2,500.00
7 wall tile (yard) - full height sf 300.00 8.00 2,400.00
8 aluminium sliding window (5'x6') sf 30.00 lump sum 600.00
9 inlet & outlet piping system set 3.00 250.00 750.00
10 light fitting installation (labour only) set 25.00 10.00 250.00
11 ceiling fan installation (labour only) set 4.00 20.00 80.00
12 loose fitting installation (labour only) lump sum 160.00
13 aircond copper pipe & drain pipe
a) 1.0hp set 1.00 600.00 600.00
b) 1.5hp set 1.00 850.00 850.00
14 making good wall plastering for which hacked. set 1.00 lump sum 250.00
Total is about RM11,515
which is totally over my budget.
i cant find any reference price in google so i need those who know the price help me.
thanks.