7core x 2.5mm cable for gate..Sufficient?
|
TStiensong
|
Sep 7 2011, 11:09 AM, updated 15y ago
|
|
Hi
I just installed
a) Auto Gate point using 7 core x 2.5mm PVC/SWA/PVC cable buried underground b) Gate Light point using 2 core x 1.5mm PVC/SWA/PVC cable buried underground c) Door bell point using 2 core x 1.5mm PVC/SWA/PVC cable burier underground
I read some people said 11 core armored cable for the gate but mine only have 7 core...So, is it sufficient? any disadvantage or problem that I may face in the future? I have been asked the contractor about this before install but he insisted 7 core was enough...
Anyone please give some explanation?
thanks a lot~
|
|
|
|
|
|
TStiensong
|
Sep 7 2011, 11:16 AM
|
|
It is not money issues....and I don't know why contractor don't want to install more core for me (more money to earn but they don't want)..
now, I am worried I may face problems in the future because of this....scared....haiz
Added on September 7, 2011, 11:17 ammay I know Autogate system usually required how many core?
This post has been edited by tiensong: Sep 7 2011, 11:17 AM
|
|
|
|
|
|
TStiensong
|
Sep 7 2011, 11:29 AM
|
|
QUOTE(Jo_da48 @ Sep 7 2011, 11:24 AM) If Look at you description, you are using 11 (7+2+2) core rights? Can be added up like that? I don't know...I thought gate itself should have 11 core?
|
|
|
|
|
|
TStiensong
|
Sep 7 2011, 12:22 PM
|
|
ooh...according to the description of my quotation, bell, light and gate are separated...if all add up, mine one should be 11 core...
|
|
|
|
|
|
TStiensong
|
Sep 7 2011, 12:57 PM
|
|
for me, renovation is a nightmare...If something doesn't done right, will end up a lot of problems..headache man...
|
|
|
|
|
|
TStiensong
|
Sep 8 2011, 10:29 AM
|
|
a) Auto Gate point using 7 core x 2.5mm PVC/SWA/PVC cable buried underground RM450 (per nos) b) Gate Light point using 2 core x 1.5mm PVC/SWA/PVC cable buried underground RM120 (per nos) c) Door bell point using 2 core x 1.5mm PVC/SWA/PVC cable burier underground RM120 (per nos)
|
|
|
|
|
|
TStiensong
|
Sep 8 2011, 02:14 PM
|
|
Hmm..based on few quotations that I received, all charge separately....
|
|
|
|
|
|
TStiensong
|
Sep 8 2011, 03:04 PM
|
|
QUOTE(feeroz @ Sep 8 2011, 02:54 PM) Per nos is per run irregardless of length? tq for sharing bro per unit regardless of length..(of course, the length already in their calculation after site measurement/inspection....and the size of project maybe a factor of price too...)
|
|
|
|
|