Kitchen extension, Approval from Majlis
|
TSiruka
|
Mar 18 2011, 04:43 PM, updated 15y ago
|
New Member
|
I've just purchased a house and would like to build a wet kitchen extension. What happens after the plans are approved by the Majlis? Do I have to inform them when the construction works start? Is there any certification by the Majlis after construction has finished?
|
|
|
|
|
|
shnia
|
Mar 18 2011, 04:54 PM
|
New Member
|
QUOTE(iruka @ Mar 18 2011, 04:43 PM) I've just purchased a house and would like to build a wet kitchen extension. What happens after the plans are approved by the Majlis? Do I have to inform them when the construction works start? Is there any certification by the Majlis after construction has finished? iruka... ya,u have to do submisson to majlis as i done before...but u dun have to inform them as u alredi have the approval form with u...
|
|
|
|
|
|
ttan777
|
Mar 18 2011, 04:59 PM
|
|
The main contractor for your extension will get all the relevant authorities approval for you.If you need assistance or design for your kitchen can PM me QUOTE(iruka @ Mar 18 2011, 05:43 PM) I've just purchased a house and would like to build a wet kitchen extension. What happens after the plans are approved by the Majlis? Do I have to inform them when the construction works start? Is there any certification by the Majlis after construction has finished?
|
|
|
|
|
|
AzimAdhwa
|
Mar 19 2011, 05:07 AM
|
Getting Started

|
1. Get renovation permit approval from majlis including plan approved by architect (own architect @ majlis panel architect) for your kitchen extension
2. After submission plan done & approved, majlis give u permit sticker to start your renovation.
3. After completion your renovation, majlis will check and make sure your kitchen extension follow their guidelines & rules based on plan submission before.
4. After majlis satisfied, CCC (Certificate of Completion and Compliance) will be given to u.
*CCC Form complete & sign by Architect
This post has been edited by AzimAdhwa: Mar 19 2011, 05:08 AM
|
|
|
|
|
|
REEN YONG
|
Mar 20 2011, 06:55 AM
|
Getting Started

|
QUOTE(AzimAdhwa @ Mar 19 2011, 05:07 AM) 1. Get renovation permit approval from majlis including plan approved by architect (own architect @ majlis panel architect) for your kitchen extension 2. After submission plan done & approved, majlis give u permit sticker to start your renovation. 3. After completion your renovation, majlis will check and make sure your kitchen extension follow their guidelines & rules based on plan submission before. 4. After majlis satisfied, CCC (Certificate of Completion and Compliance) will be given to u. *CCC Form complete & sign by Architect How long will MPPJ take to approve the plan??
|
|
|
|
|
|
AzimAdhwa
|
Mar 20 2011, 06:47 PM
|
Getting Started

|
QUOTE(REEN YONG @ Mar 20 2011, 06:55 AM) How long will MPPJ take to approve the plan??  if your plan follow their guidelines & rules normally 3 working days
|
|
|
|
|