Hi All
I have this contractor who has been renovating my apartment since Sept 2010.
Until today still notyet complete.
Is there any way action I can take against him?
Please advise.
Eleganz Concept
post Mar 3 2011, 04:48 PM

On my way
****
Senior Member
582 posts

Joined: Oct 2010
QUOTE(anakcili @ Mar 3 2011, 03:29 PM)
Hi All
  I have this contractor who has been renovating my apartment since Sept 2010.
Until today still notyet complete.
Is there any way action I can take against him?
Please advise.
*
Are you pay up to date? hold thier payment (if u still have any) and sit down to discuss when will be the confirm final completion date, if they fail to deliver the house at the date they fix, then u tell them u not going to pay them and will hire another contractor to continue your house job. and if you guy had sign in document about all this, then u can sue the contractor as well, if u wish.
TSanakcili
post Mar 3 2011, 05:11 PM

New Member
*
Junior Member
22 posts

Joined: Feb 2009
QUOTE(Eleganz Concept @ Mar 3 2011, 04:48 PM)
Are you pay up to date? hold thier payment (if u still have any) and sit down to discuss when will be the confirm final completion date, if they fail to deliver the house at the date they fix, then u tell them u not going to pay them and will hire another contractor to continue your house job. and if you guy had sign in document about all this, then u can sue the contractor as well, if u wish.
*
Hi
I paid RM 45K out of RM 50K.
If I am to get new contractor the price might be more than RM 5K.

AzimAdhwa
post Mar 3 2011, 08:30 PM

Getting Started
**
Junior Member
84 posts

Joined: Jan 2008


what type of work delay for 5k balance?
TSanakcili
post Mar 3 2011, 08:43 PM

New Member
*
Junior Member
22 posts

Joined: Feb 2009
QUOTE(AzimAdhwa @ Mar 3 2011, 08:30 PM)
what type of work delay for 5k balance?
*
Work balance are as follow

1) Stainless stell door (59 inch)
2) Bird cage
3) Toilet door x 2
4) Kitchen door
5) Dry area door
6) Kitchen cabinet
7) Balcony grill x 2
8) Windows grill x 1


AzimAdhwa
post Mar 3 2011, 09:56 PM

Getting Started
**
Junior Member
84 posts

Joined: Jan 2008


QUOTE(anakcili @ Mar 3 2011, 08:43 PM)
Work balance are as follow

1) Stainless stell door (59 inch)
2) Bird cage
3) Toilet door x 2
4) Kitchen door
5) Dry area door
6) Kitchen cabinet
7) Balcony grill x 2
8) Windows grill x 1
*
lots of mistake here..progress claim should be manage by u actually..be straight to the contractor..to hire new contractor i think costly

 