QUOTE(Happy6398 @ Jul 6 2015, 12:16 PM)
Hi,

I just joined the group. pending for approval. thumbup.gif
monios
post Jul 7 2015, 12:03 PM

New Member
*
Junior Member
49 posts

Joined: Jun 2014
Cannot share here... got LHDN people reading this... shakehead.gif

QUOTE(Matheus271 @ Jul 6 2015, 01:54 PM)
Mind to share how much u purchased last time after discount pls?
*
khleow
post Jul 8 2015, 01:21 PM

New Member
*
Newbie
2 posts

Joined: Apr 2013


hi guys, for those of you who have bought the property under DIBS scheme, please note that you need not to pay Interest Payment until actual Vacant Possession had taken placed. OSK has bull dozed you by asking you pay the Interest Payment on the date the letter had issued. Please note that most of you may take several weeks to have taken Vacant Possesion, why let OSK abuse you !

So don't pay the Interest Payment to the bank from the date of VP letter issued, but only from the date VP had taken placed. Please spread this word to all your friends.
shisham
post Jul 8 2015, 04:26 PM

New Member
*
Junior Member
47 posts

Joined: May 2013
QUOTE(khleow @ Jul 8 2015, 01:21 PM)
hi guys, for those of you who have bought the property under DIBS scheme, please note that you need not to pay Interest Payment until actual Vacant Possession had taken placed. OSK has bull dozed you by asking you pay the Interest Payment on the date the letter had issued. Please note that most of you may take several weeks to have taken Vacant Possesion, why let OSK abuse you !

So don't pay the Interest Payment to the bank from the date of VP letter issued, but only from the date VP had taken placed. Please spread this word to all your friends.
*
Please be aware that there is certain clause under the SPA that even key is not handover, VP is considered after 2 weeks (if not mistaken) from the date of the notice for VP.

The interest that you are suppose to pay under the VP letter mostly because of the late first drawdown from the bank. however, you can challenge them on this if you have proof that this is non of your fault. As in my case, this is their lawyer fault for not sending the letter to bank or late sending.

khleow
post Jul 8 2015, 06:23 PM

New Member
*
Newbie
2 posts

Joined: Apr 2013


QUOTE(shisham @ Jul 8 2015, 05:26 PM)
Please be aware that there is certain clause under the SPA that even key is not handover, VP is considered after 2 weeks (if not mistaken) from the date of the notice for VP.

The interest that you are suppose to pay under the VP letter mostly because of the late first drawdown from the bank. however, you can challenge them on this if you have proof that this is non of your fault. As in my case, this is their lawyer fault for not sending the letter to bank or late sending.
*
Thanks Shisham for info.
In my case, there is a clause in the letter that interest payment will count from the date it issue written notification, in this case , they put it on 22nd June. But most people would receive the letter on 22nd June, thus OSK should continue to pay the interest until Vacant Possession. Now, the bank is chasing me to pay the interest from 22nd June, do you think it is fair ?

blowwater101
post Jul 10 2015, 05:16 PM

Regular
******
Senior Member
1,224 posts

Joined: Sep 2011
May I know normally how long does it take for them to rectify the defects ?
spydermind
post Jul 10 2015, 05:25 PM

Regular
******
Senior Member
1,166 posts

Joined: Dec 2010
about 2-3 weeks.
blowwater101
post Jul 10 2015, 05:27 PM

Regular
******
Senior Member
1,224 posts

Joined: Sep 2011
QUOTE(spydermind @ Jul 10 2015, 05:25 PM)
about 2-3 weeks.
*
Thanks bro, still acceptable.

before they fix the defects can we start minor reno?

This post has been edited by blowwater101: Jul 10 2015, 05:33 PM
blowwater101
post Jul 12 2015, 12:27 AM

Regular
******
Senior Member
1,224 posts

Joined: Sep 2011
QUOTE(blowwater101 @ Jul 10 2015, 05:27 PM)
Thanks bro, still acceptable.

before they fix the defects can we start minor reno?
*
found my answer today, defects promised to be attended and solved within a month.

but reno might void the warranty biggrin.gif
spydermind
post Jul 12 2015, 08:42 AM

Regular
******
Senior Member
1,166 posts

Joined: Dec 2010
Reno is OK but if it really minor defect like hairline cracking or paint...then you might want to start the reno now and fix it yourself ylife you don't want to wait
noblebaby
post Jul 12 2015, 09:09 AM

Look at all my stars!!
*******
Senior Member
4,921 posts

Joined: Oct 2012


Best is keep chasing them and visit your unit frequently to check the rectification... If not good, report straightaway.

QUOTE(blowwater101 @ Jul 12 2015, 12:27 AM)
found my answer today, defects promised to be attended and solved within a month.

but reno might void the warranty biggrin.gif
*
blowwater101
post Jul 12 2015, 10:28 PM

Regular
******
Senior Member
1,224 posts

Joined: Sep 2011
QUOTE(noblebaby @ Jul 12 2015, 09:09 AM)
Best is keep chasing them and visit your unit frequently to check the rectification... If not good, report straightaway.
*
yes will do.

in Overall im satisfied with my unit, workmanship is good for me...some minor defects are acceptable...
shisham
post Jul 13 2015, 09:38 AM

New Member
*
Junior Member
47 posts

Joined: May 2013
QUOTE(khleow @ Jul 8 2015, 06:23 PM)
Thanks Shisham for info.
In my case, there is a clause in the letter that interest payment will count from the date it issue written notification, in this case , they put it on 22nd June. But most people would receive the letter on 22nd June, thus OSK should continue to pay the interest until Vacant Possession. Now, the bank is chasing me to pay the interest from 22nd June, do you think it is fair ?
*
i just read back my VP letter. yes, the DIBS shall cease on the date of VP itself. or acceptance of the letter date.

your case can be considered mild. i have been paying my monthly payment but yet be able to enjoy the house. rectification still not 100% satisfaction after 8 months. as mentioned before, cracks re-occuring (after days of hacking / plastering) around the house. now i am thinking if it is really a structure issue that cause the cracks.
noblebaby
post Jul 13 2015, 01:23 PM

Look at all my stars!!
*******
Senior Member
4,921 posts

Joined: Oct 2012


any nice pic to share?

QUOTE(blowwater101 @ Jul 12 2015, 10:28 PM)
yes will do.

in Overall im satisfied with my unit, workmanship is good for me...some minor defects are acceptable...
*
blowwater101
post Jul 13 2015, 02:55 PM

Regular
******
Senior Member
1,224 posts

Joined: Sep 2011
nothing much...just a bare unit...haha

environment is just like those who sharing in iproperty....but it will getting better bcos some renovation work is still under going....satisfied with the gym facilities, it is quite complete compare to other gym facilities in other condo

This post has been edited by blowwater101: Jul 13 2015, 02:55 PM
Miwqa
post Jul 13 2015, 04:24 PM

New Member
*
Junior Member
33 posts

Joined: Mar 2007
Hi guys, i just received invoice letter for VP (phase 2). Initially i thought i just want to get over and pay the late payment charges until i saw the invoice amounted to rm 2k, what donyou guys think? Any advice?


Attached thumbnail(s)
Attached Image
Zres
post Jul 13 2015, 04:36 PM

On my way
****
Senior Member
557 posts

Joined: Nov 2013


very disappointed with OSK property.... many phase 2 resident parking were allocated outside the block...which suppose should be the visitor parking in the masterplan...the parking is not fully covered and linked to the block...

In the master plan, that place is visitor carpark...
center_ob
post Jul 13 2015, 07:16 PM

New Member
*
Junior Member
5 posts

Joined: Jul 2015
QUOTE(Zres @ Jul 13 2015, 04:36 PM)
very disappointed with OSK property.... many phase 2 resident parking were allocated outside the block...which suppose should be the visitor parking in the masterplan...the parking is not fully covered and linked to the block...

In the master plan, that place is visitor carpark...
*
Really?

If like that really disappoint with OSK. mad.gif
Zres
post Jul 13 2015, 10:52 PM

On my way
****
Senior Member
557 posts

Joined: Nov 2013


QUOTE(center_ob @ Jul 13 2015, 07:16 PM)
Really?

If like that really disappoint with OSK.  mad.gif
*
Yes, this is true.

U may see more complaints coming soon. some residents car park with lot number but not even covered.
monios
post Jul 14 2015, 10:11 AM

New Member
*
Junior Member
49 posts

Joined: Jun 2014
If this happen to me I will complain and request for in-block covered parking. How can they do like this. There must be something wrong with the planning...

QUOTE(Zres @ Jul 13 2015, 04:36 PM)
very disappointed with OSK property.... many phase 2 resident parking were allocated outside the block...which suppose should be the visitor parking in the masterplan...the parking is not fully covered and linked to the block...

In the master plan, that place is visitor carpark...
*

95 Pages « < 56 57 58 59 60 > » Top
 

Change to:
| Lo-Fi Version
0.0369sec    0.61    6 queries    GZIP Disabled
Time is now: 3rd December 2025 - 06:52 AM