Welcome Guest ( Log In | Register )

Outline · [ Standard ] · Linear+

 Factory Construction Cost

views
     
skng03
post Nov 16 2010, 10:56 PM

Regular
******
Senior Member
1,450 posts

Joined: Oct 2008


QUOTE(keith_hjinhoh @ Nov 16 2010, 01:33 PM)
Hey guys,

Recently a friend of mine purchase a plot of land and he's interested to construct a factory on that plot of land.

But I remain skeptical about the viability of the project, as

1. We are not builders. The total cost of construction and land maybe more expensive than getting a new factory

2. He maybe under-budget. As the construction material getting more expensive, the budget maybe burst and the whole construction will have to stalled.

Therefore, I'm here to ask,

Roughly what's the cost of construction a high ceiling 1.5 storey factory on a land of 7000sqft? Are using steel to construct factory cost much cheaper?

-> That plot of land already have water, electricity supply.

-> It's a uncleared barren land.

Thank you. notworthy.gif  notworthy.gif

Hopefully there's some QS expert in the forum able to give their comments notworthy.gif
*
7000ft2 land hmm.gif hmm.gif minus 20ft set back front, 10ft set back 2side & rear, the factory ground floor build up area will be less than 3500ft2, assuming u build 2 storey office with 1000 ft2 for 1st floor, the total build up area +- 4500ft2 only.

rough estimation will be rm250++/ ft2 for such small project nod.gif nod.gif very much depend on the land condition, ie flat/ slope, cut/fill, soft/hard/rock ground, piling/ pad footing...........


skng03
post Nov 17 2010, 04:27 PM

Regular
******
Senior Member
1,450 posts

Joined: Oct 2008


QUOTE(keith_hjinhoh @ Nov 17 2010, 10:28 AM)
Is this the local council ruling? But I have seen factory fully utilise all the land area.

The rough estimation of 250/sqft is brick, concrete construction? Would it be cheaper, if it's build using portal frame and steel design?
*
the set back things is requirement, unless u want to build a illegal factory icon_rolleyes.gif

rm250/ sft is just example, without any info/ drawing....

portal frame/ steel structure/ pre-engineering may/ may not cheap, all depend on your requirement. btw, this is factory/ warehouse/ show room/ store.............. blink.gif

 

Change to: