QUOTE(user1984 @ Jul 8 2012, 11:09 AM)
this project launched 2010 and until now the construction of the condo is only upto car park level??? when was the s&p signed?
if this is true, luckily not vested into this few years back, if not really loosing time/money...
If not mistaken , signing on early of Q2 2011 ?if this is true, luckily not vested into this few years back, if not really loosing time/money...
Added on July 8, 2012, 1:47 pmm2c..
Highrise completion period should be 3 years ..
Structural frame for The floor after transfer floor required 10-14 days to complete ... They resumed the constrcution works 2 months ago...The block next to landed roughly taken 2 weeks to complete a floor .. So that the progress still reasonable .. 17 floors required 17*2 weeks = 34 weeks ... Architectural works required 6-8months for Highrise ... main drain and partial of the road already completed , which means the infra works time frame will be shorter.. Based on SNP Still hv 70 weeks to the targeted completion date .. I think slow down of the progress on condo is due to their strategy ..the semiD sales are not that good ... But the semi D is under dibs ... Longer construction time the developer need to absorb more Interest from bank..
They stopped on the floor before transfer floor almost 2 months ... But their landed move faster after that ..
Based on hda act .. Landed is 24 months , condo 36 months ?