post Oct 29 2011, 11:32 PM

Casual
***
Junior Member
462 posts

Joined: Oct 2004
QUOTE(Onn88 @ Oct 29 2011, 08:27 PM)
Went to the showroom today. Left behind 480k unit which facing another block's wall. 5% disc only.
*
What is the taking rate now? How many units left? smile.gif


Cheers
tls
post Oct 29 2011, 11:54 PM

New Member
*
Junior Member
15 posts

Joined: May 2009
If someone got unit to let go?? Pls PM me with detail...
Cheer....


Onn88
post Oct 30 2011, 07:21 AM

Getting Started
**
Junior Member
216 posts

Joined: Aug 2011
QUOTE(jssl @ Oct 29 2011, 11:32 PM)
What is the taking rate now? How many units left? smile.gif
Cheers
*
Only left few unit that facing the block A wall and 2 unit of ground floor unit which have extra land of 600s.f. at the balcony cause they are at ground floor @ RM580k

This post has been edited by Onn88: Oct 30 2011, 07:23 AM
jssl
post Nov 20 2011, 11:35 AM

Casual
***
Junior Member
462 posts

Joined: Oct 2004
QUOTE(Onn88 @ Oct 30 2011, 07:21 AM)
Only left few unit that facing the block A wall and 2 unit of ground floor unit which have extra land of 600s.f. at the balcony cause they are at ground floor @ RM580k
*
Ohh I see
Thanks for the info! smile.gif
S H Tan
post Jan 18 2012, 03:23 AM

New Member
*
Newbie
1 posts

Joined: Jan 2012


I have a unit for sale if any interested.
jcyvonne
post Feb 9 2012, 10:17 PM

New Member
*
Newbie
1 posts

Joined: Feb 2012
QUOTE(S H Tan @ Jan 18 2012, 03:23 AM)
I have a unit for sale if any interested.
*
Hi i m interested. Pls pm me at jcyvonne@hotmail.com
Chris Chew
post Feb 9 2012, 10:35 PM

10k Club
********
Senior Member
10,387 posts

Joined: Dec 2011


Wow, so fast and so keen?

USJ One Park completed dy meh?
jssl
post Apr 6 2012, 11:30 PM

Casual
***
Junior Member
462 posts

Joined: Oct 2004
Photo update as per today :

user posted image

user posted image


Cheers

This post has been edited by jssl: Apr 10 2012, 07:39 PM
ally80
post Jun 12 2012, 03:20 PM

Getting Started
**
Junior Member
86 posts

Joined: Jan 2009


QUOTE(S H Tan @ Jan 18 2012, 03:23 AM)
I have a unit for sale if any interested.
*
PLS PM ME DETAILS..id unit still available..thanks
kwaytiau
post Jun 21 2012, 08:17 PM

Getting Started
**
Junior Member
50 posts

Joined: Aug 2006
From: Kuala Lumpur MAL


QUOTE(S H Tan @ Jan 18 2012, 03:23 AM)
I have a unit for sale if any interested.
*
please PM the offer/price/unit/sqft ?

I m interested.
tatagal
post Jul 7 2012, 09:15 PM

Getting Started
**
Junior Member
282 posts

Joined: Feb 2011
Anyone knows whether their show unit in the construction site still open?
user1984
post Jul 8 2012, 11:09 AM

Getting Started
**
Junior Member
153 posts

Joined: Aug 2011
this project launched 2010 and until now the construction of the condo is only upto car park level??? when was the s&p signed?

if this is true, luckily not vested into this few years back, if not really loosing time/money...
Chris Chew
post Jul 8 2012, 11:46 AM

10k Club
********
Senior Member
10,387 posts

Joined: Dec 2011
QUOTE(user1984 @ Jul 8 2012, 11:09 AM)
this project launched 2010 and until now the construction of the condo is only upto car park level??? when was the s&p signed?

if this is true, luckily not vested into this few years back, if not really loosing time/money...
*
Any idea y so slow???

Almost forget got such building in USJ, aside the landed which almost can complete dy.


user1984
post Jul 8 2012, 12:35 PM

Getting Started
**
Junior Member
153 posts

Joined: Aug 2011
QUOTE(Chris Chew @ Jul 8 2012, 11:46 AM)
Any idea y so slow???

Almost forget got such building in USJ, aside the landed which almost can complete dy.
*
i saw the progress from the last posting attached photo...no idea y it is sooo slow...pity to the investor...
yewfei1128
post Jul 8 2012, 01:23 PM

New Member
*
Junior Member
40 posts

Joined: Mar 2008
QUOTE(user1984 @ Jul 8 2012, 11:09 AM)
this project launched 2010 and until now the construction of the condo is only upto car park level??? when was the s&p signed?

if this is true, luckily not vested into this few years back, if not really loosing time/money...
*
If not mistaken , signing on early of Q2 2011 ?


Added on July 8, 2012, 1:47 pmm2c..
Highrise completion period should be 3 years ..
Structural frame for The floor after transfer floor required 10-14 days to complete ... They resumed the constrcution works 2 months ago...The block next to landed roughly taken 2 weeks to complete a floor .. So that the progress still reasonable .. 17 floors required 17*2 weeks = 34 weeks ... Architectural works required 6-8months for Highrise ... main drain and partial of the road already completed , which means the infra works time frame will be shorter.. Based on SNP Still hv 70 weeks to the targeted completion date .. I think slow down of the progress on condo is due to their strategy ..the semiD sales are not that good ... But the semi D is under dibs ... Longer construction time the developer need to absorb more Interest from bank..

They stopped on the floor before transfer floor almost 2 months ... But their landed move faster after that ..
Based on hda act .. Landed is 24 months , condo 36 months ?


This post has been edited by yewfei1128: Jul 8 2012, 01:47 PM
jssl
post Jul 14 2012, 01:12 AM

Casual
***
Junior Member
462 posts

Joined: Oct 2004
QUOTE(yewfei1128 @ Jul 8 2012, 01:23 PM)
If not mistaken , signing on early of Q2 2011 ?


Added on July 8, 2012, 1:47 pmm2c..
Highrise  completion period should be 3 years ..
Structural  frame for The floor after transfer floor required 10-14 days to complete ... They resumed the constrcution works 2 months ago...The block next to landed roughly taken 2 weeks to complete a floor .. So that the progress still reasonable .. 17 floors required 17*2 weeks = 34 weeks ... Architectural works required 6-8months for Highrise ...  main drain and partial of the road already completed , which means the infra works time frame will be shorter.. Based on SNP  Still hv 70 weeks to the targeted completion date .. I think slow down of the progress on condo is due to their strategy ..the semiD sales are not that good ... But the semi D is under dibs ... Longer construction time the developer need to absorb more Interest from bank..

They stopped on the floor before transfer floor almost 2 months ... But their landed move faster after that ..
Based on hda act .. Landed is 24 months , condo 36 months ?
*
Thanks for the details explanation ~

Well, we shall wait & see whether those purchaser is "losing" money or not after few years, lol



Cheers
coolman82
post Jul 22 2012, 12:25 AM

Regular
******
Senior Member
1,518 posts

Joined: Jun 2011
QUOTE(jssl @ Jul 14 2012, 01:12 AM)
Thanks for the details explanation ~

Well, we shall wait & see whether those purchaser is "losing" money or not after few years, lol
Cheers
*
Did you buy any unit there?
1282009
post Jul 22 2012, 11:32 AM

Look at all my stars!!
*******
Senior Member
4,229 posts

Joined: Jan 2009
"Price - 1242 sf (RM369000 onwards), 892 sf (RM297000 onwards), price increase per floor (RM1000)"

With the launching price like above before discount, I doubt buyers will be losing money upon VP. Who's the developer again? hmm.gif


user1984
post Jul 22 2012, 11:50 AM

Getting Started
**
Junior Member
153 posts

Joined: Aug 2011
for this prop, if it could not complete in the year of 2013, it is a big lost to the investor...unless it could appreciate more than 100% upon vp assuming it vp at the year of 2015...
1282009
post Jul 22 2012, 12:00 PM

Look at all my stars!!
*******
Senior Member
4,229 posts

Joined: Jan 2009
QUOTE(user1984 @ Jul 22 2012, 11:50 AM)
for this prop, if it could not complete in the year of 2013, it is a big lost to the investor...unless it could appreciate more than 100% upon vp assuming it vp at the year of 2015...
*
LAD? shocking.gif