24/10/2010 - Paid 10% downpayment
12/01/2011 - Loan offer letter produced from bank, and signed
16/01/2011 - S & P signed
20/01/2011 - Letter from developer saying approval of loan from bank, and demanding to pay the amount difference between loan amount and purchase price
25/04/2011 - S & P stampped
25/04/2011 - Loan agreement stampped
Progress claim Date claim Due Date (21 days) Date Paid Over Due Note
10% 24/10/2010 24/12/2010 24/10/2010 No 10% downpayment
20% 14/11/2010 04/12/2010 02/12/2010 No Self paid as there's issue with bank loan
35% 15/12/2010 05/01/2011 26/01/2011 Yes Self paid as there's issue with bank loan
30/05/2011 Yes Late disbursement by bank
45% 09/01/2011 29/01/2011 30/05/2011 Yes Late disbursement by bank
55% 26/01/2011 15/02/2011 30/05/2011 Yes Late disbursement by bank
75% 27/03/2011 16/04/2011 30/05/2011 Yes Late disbursement by bank
80% 13/06/2011 03/07/2011 10/07/2011 Yes Late disbursement by bank
Based on the information above, is it the late disbursement by bank is due to the delay from the bank/lawyer side? Since the loan offer letter 12/01/2011 already signed and developer already noticed of approval of our bank loan on 20/01/2011?
If the late disbursement by bank is due to the delay by bank/lawyer, i ssupose the late charges should not be charged to me?
Please let me know if any further information is needed.
Thanks a lot!
Oct 26 2011, 06:05 PM