1120 Park Avenue - PJ South, any comments?
|
brianchinh
|
Sep 23 2010, 03:57 PM
|
New Member
|
QUOTE(moonh @ Sep 23 2010, 12:15 PM) I think it should be a new project by Wisma Peter which is yet to be launched. Btw, the project info for 1120 PA is here: http://ehome.kpkt.gov.my/ehome/DetailProje...0PARK%20AVENUE#and the analysis chart of 1120 PA buyers by race: http://ehome.kpkt.gov.my/ehome/LaporanJual...20PARK%20AVENUEThe data shows the units still available are 74. I believe the figure was last updated on June 2010. This post has been edited by brianchinh: Sep 23 2010, 04:33 PM
|
|
|
|
|
|
brianchinh
|
Oct 7 2010, 01:00 AM
|
New Member
|
QUOTE(kentlhk @ Oct 6 2010, 11:49 PM) Great job! I heard there is Giant near to this condo in the near future.. is tat true?? The Bintang chain has been bought over by Giant. N there is one Bintang outlet in Sri Manja, considering quite near the condo too.
|
|
|
|
|
|
brianchinh
|
Oct 8 2010, 06:33 PM
|
New Member
|
QUOTE(kentlhk @ Oct 7 2010, 10:57 PM) wat I mean is they goin to build new giant at that area... Added on October 7, 2010, 11:00 pmwat i heard is the land next to new petronas (across the road) where the land is fenced up.. Giant or Tesco doesnt matter.... hopefully this is true.. IC. That plot of land u mentioned indeed has a MBPJ notice board there...proposing of building a 1.5 storey hypermarket. Hmm, but 1120 PA still don't have any MBPJ notice board. Wonder why huh....
|
|
|
|
|
|
brianchinh
|
Oct 24 2010, 01:10 PM
|
New Member
|
Hi 1120 PA buyers, Here are the the photos of the construction site which I took in this morning (24/10/10).     Good news is that the construction signboard is finally up! It is not along the road if u are coming from the turn where the Shell is at ur left. U have to turn into the small road after passing the Petronas station. A few workers were working there during my visit. Hopefully the project will run smoothly and complete in time. This post has been edited by brianchinh: Oct 25 2010, 09:48 AM
|
|
|
|
|
|
brianchinh
|
Oct 25 2010, 03:44 PM
|
New Member
|
QUOTE(WEE2000 @ Oct 25 2010, 01:45 PM) the main con is left empty, is it? pemaju n kontraktor utama is same right? anyway, its not to my concern, as long as it goes smoothhly.. According the info from the Portal e-Home, the main contractor is ZEUS DEVELOPMENT (WP) SDN. BHD. Add: WISMA GOSHEN, 2ND FLOOR, 60 & 62, JALAN SS 22/21, DAMANSARA JAYA, 47400 PETALING JAYA No. Tel : 03-77829988 Don't know why that column is left empty.
|
|
|
|
|
|
brianchinh
|
Oct 26 2010, 12:25 AM
|
New Member
|
QUOTE(0106127 @ Oct 25 2010, 08:32 PM) Ya gosh, it has been 10 months since the project started selling.
|
|
|
|
|
|
brianchinh
|
Dec 1 2010, 09:27 AM
|
New Member
|
Kemc1120, thanks for your great efforts... I tried to call En Aidy (or Ardy) but no one picked up too. Do you happened to know where is this Jabantan Memantau located? If we know the add, whoever is free can just go to lodge a complain...
|
|
|
|
|
|
brianchinh
|
Feb 13 2011, 07:28 PM
|
New Member
|
QUOTE(vincemy @ Feb 12 2011, 04:41 PM) The project at 1120 is now in full swing. The workers have removed the formwork for the ground beams at Block #1. In the foreground of the 1st picture you will notice that the precast concrete culvert pipes and manholes have been erected. In the last 2 photos you can also notice some activities at Blocks #3 & #4. Attached are photos taken at 3:00pm on 12th Feb 2011. Cheers Wow, thanks for the constant photo update, Vincemy This post has been edited by brianchinh: Feb 13 2011, 07:28 PM
|
|
|
|
|
|
brianchinh
|
Feb 17 2011, 09:32 PM
|
New Member
|
The NPE toll cut down is really a good news coz I use it everyday!
|
|
|
|
|
|
brianchinh
|
Feb 25 2011, 09:41 PM
|
New Member
|
QUOTE(vincemy @ Feb 25 2011, 06:24 PM) I have received an email reply from the Management for 1120 Park Avenue today and it reads: "We regret to inform that we shall not be offering the additional service of providing further power points, water heaters and etc. We can however, help to recommend some qualified electricians should you not have one already."  I wrote an email to them too and they gave the same reply. Apart from that, i inquired of the ceiling height. Below is the 1120 reply on that: "In terms of the height of the ceiling, it is approximately over 9 feet."
|
|
|
|
|
|
brianchinh
|
Apr 23 2011, 11:52 PM
|
New Member
|
Vincemy, really appreciated your consistent update! I assume ur picture no.21, 22 & 23 are showing the car park for phase 2 blocks?
|
|
|
|
|
|
brianchinh
|
Apr 24 2011, 10:07 AM
|
New Member
|
I went to the site this morning about 8.15 a.m and there were a lots of construction activities going-on. Although it is a Sunday morning but there are definitely more than 20 workers working all over the site. Good sign to be seen.
|
|
|
|
|