During MPSJ’s full board meeting, several councillors requested for a detailed briefing on the LRT extension project from Syarikat Prasarana Negara Bhd (Prasarana) following complaints of some earth works near Subang Jaya KTM Station.
“We will invite Prasarana to brief the MPSJ councillors on the latest development next month,” said Adnan.
Following Prasarana’s submission for the planning permission of seven stations last month, Adnan said the MPSJ had given
approval for two stations in Kinrara.“The other five were not approved due to insufficient technical details for the stations,” he said.
“Hence, Prasarana has to resubmit the station design and details.
“Once the One Stop Centre Committee has given its approval, they can start building the LRT structures.”
source:
http://thestar.com.my/metro/story.asp?file...320&sec=centralIs it one of the 2 approved station is at TZ? if yes